National Spherical Torus Experiment (NSTX) NBI BL2 Upgrade Project

NSTX CSU Web Pages  

Overview| Conferences |

NCSX FTP Sites  

    |

Navigation Trail  

Publications and Presentations > Meetings and Presentations > Project Meetings => NBI BL2
CY-2009 Meetings

Note:

Documentation is organized by meeting month and day.

 

The relevant WBS is in parentheses - (6) means WBS 6 in our shorthand notation:

(SIT) indicates a Systems Integration Team meeting.

(CS) indicates a monthly Cost and Schedule Review.

(Engr) indicates a project-wide Engineering meeting.

(Matl) indicates a materials test meeting.

(CA) indicates a Critical Activities status meeting

(PS) indicates the weekly Project Status telecon

(CCB) indicates a Change Control Board meeting

(OFES) indicates a meeting with OFES.

(DC) indicates Dimensional Control

(OSF) indicates On-site Fabrication

(Weld) indicates a Weld Trials.

(PM) indicates weekly Project Manager meeting with entire project.

(PS) indicates weekly status update

(WS) indicates a project workshop

 

January   
February

06 (PS) 13 (PS) 20 (PS)

March 09 (PS) 13 (PS) 20 (PS) 27 (PS)
April

03 (PS) 10 (PS) 16 (PS) 24 (PS)

May 01 (PS) 08 (PS) 15 (PS) 21 (PS) 29 (PS)
June

05 (PS) 12 (PS) 19 (PS) 26 (PS)

July 01 (PS) 10 (PS) 17 (PS) 24 (PS) 31 (PS)
August 07 (PS) 14 (PS) 21 (PS) 28 (PS)
September 02 (Photos) 18 (PS) 25 (PS)
October 09 (PS) 16 (PS) 23 (PS) 28/29 (CDR)
November 06 (PS) 13 (PS) 20 (PS) 25 (PS)
December 04 (PS) 11 (PS) 18 (PS)
 
CY-2010 Meetings

Note:

Documentation is organized by meeting month and day.

 

The relevant WBS is in parentheses - (6) means WBS 6 in our shorthand notation:

(SIT) indicates a Systems Integration Team meeting.

(CS) indicates a monthly Cost and Schedule Review.

(Engr) indicates a project-wide Engineering meeting.

(Matl) indicates a materials test meeting.

(CA) indicates a Critical Activities status meeting

(PS) indicates the weekly Project Status telecon

(CCB) indicates a Change Control Board meeting

(OFES) indicates a meeting with OFES.

(DC) indicates Dimensional Control

(OSF) indicates On-site Fabrication

(Weld) indicates a Weld Trials.

(PM) indicates weekly Project Manager meeting with entire project.

(PR) indicates a Project Review

(PS) indicates weekly status update

(WS) indicates a project workshop

 

January  15 (PS) 22 (PS) 29 (PS)
February

05 (PS) 17 (PR) 19 (PS)

March 05 (PS) 12 (PS) 25 (PS)
April

02 (PS) 09 (PS) 16 (PS) 23 (PS) 30 (PS)

May 07 (PS) 14 (PS) 21 (PS)
June

04 (PS) 11 (PS) 18 (PS) 25 (PS)

July 09 (PS) 16 (PS) 30 PS)
August 13 (PS) 20 (PS) 27 (PS)
September 17 (PS) 24 (PS)
October 01 (PS) 08 (PS) 15 (PS)
November 05 (PM) 12 (PS)
December 03 (PS) 10 (PS)
CY-2011 Meetings

Note:

Documentation is organized by meeting month and day.

 

The relevant WBS is in parentheses - (6) means WBS 6 in our shorthand notation:

(SIT) indicates a Systems Integration Team meeting.

(CS) indicates a monthly Cost and Schedule Review.

(Engr) indicates a project-wide Engineering meeting.

(Matl) indicates a materials test meeting.

(CA) indicates a Critical Activities status meeting

(PS) indicates the weekly Project Status telecon

(CCB) indicates a Change Control Board meeting

(OFES) indicates a meeting with OFES.

(DC) indicates Dimensional Control

(OSF) indicates On-site Fabrication

(Weld) indicates a Weld Trials.

(PM) indicates weekly Project Manager meeting with entire project.

(PR) indicates a Project Review

(PS) indicates weekly status update

(WS) indicates a project workshop

 

January  07 (PS) 14 (PS) 28 (PS)
February

04 (PS) 11 (PS) 18 (PS) 25 (PS)

March 04 (PS) 11 (PS) 25 (PS)
April

01 (PS) 15 (PS) 22 (PS) 29 (PS)

May 06 (PS) 13 (PS) 20 (PS)
June

03 (PS) 10 (PS) 17 (PS)

July 01 (PS) 08 (PS) 15 (PS) 22 (PS) 29 (PS)
August 05 (PS) 19 (PS) 26 (PS)
September 02 (PS) 22 (PS)
October 07 (PS) 14 (PS) 21 (PS) 28 (PS)
November 04 (PS) 11 (PS), 18 (PS)
December 02 (PS) 09 (PS) 16 (PS)

 

CY-2012 Meetings

Note:

Documentation is organized by meeting month and day.

 

The relevant WBS is in parentheses - (6) means WBS 6 in our shorthand notation:

(SIT) indicates a Systems Integration Team meeting.

(CS) indicates a monthly Cost and Schedule Review.

(Engr) indicates a project-wide Engineering meeting.

(Matl) indicates a materials test meeting.

(CA) indicates a Critical Activities status meeting

(PS) indicates the weekly Project Status telecon

(CCB) indicates a Change Control Board meeting

(OFES) indicates a meeting with OFES.

(DC) indicates Dimensional Control

(OSF) indicates On-site Fabrication

(Weld) indicates a Weld Trials.

(PM) indicates weekly Project Manager meeting with entire project.

(PR) indicates a Project Review

(PS) indicates weekly status update

(WS) indicates a project workshop

 

January  06 (PS) 13 (PS) 20 (PS) 27 (PS)
February 03 (PS) 10 (PS) 17 (PS) 24 (PS)
March 02 (PS) 09 (PS) 16 (PS) 23 (PS) 30 (PS)
April 06 (PS) 13 (PS) 20 (PS) 27 (PS)
May 04 (PS) 11 (PS) 18 (PS) 25 (PS)
June

01 (PS) 08 (PS) 15 (PS) 22 (PS) 29 (PS)

July 13 (PS) 20 (PS) 27 (PS)
August 03 (PS) 10 (PS) 17 (PS) 31 (PS)
September  
October 12 (PS) 19 (PS) 26 (PS)
November 02 (PS) 09 (PS) 16 (PS) 30 (PS)
December 07 (PS) 21 (PS)

 

CY-2013 Meetings

Note:

Documentation is organized by meeting month and day.

 

The relevant WBS is in parentheses - (6) means WBS 6 in our shorthand notation:

(SIT) indicates a Systems Integration Team meeting.

(CS) indicates a monthly Cost and Schedule Review.

(Engr) indicates a project-wide Engineering meeting.

(Matl) indicates a materials test meeting.

(CA) indicates a Critical Activities status meeting

(PS) indicates the weekly Project Status telecon

(CCB) indicates a Change Control Board meeting

(OFES) indicates a meeting with OFES.

(DC) indicates Dimensional Control

(OSF) indicates On-site Fabrication

(Weld) indicates a Weld Trials.

(PM) indicates weekly Project Manager meeting with entire project.

(PR) indicates a Project Review

(PS) indicates weekly status update

(WS) indicates a project workshop

 

January  04 (PS) 11 (PS) 18 (PS) 25 (PS)
February 01 (PS) 08 (PS) 21 (PS)
March 08 (PS) 15 (PS) 22 (PS)
April 05 (PS) 12 (PS) 19 (PS) 26 (PS)
May 03 (PS) 10 (PS) 24 (PS) 31 (PS)
June

07 (PS) 14 (PS)

July 05 (PS) 12 (PS) 19 (PS) 26 (PS)
August 08 (PS) 16 (PS) 23 (PS) 29 (PS)
September 13 (PS) 20 (PS) 20 (PS)
October 04 (PS) 11 (PS) 18 (PS)
November 01 (PS) 08 (PS) 15 (PS) 22 (PS)
December 06 (PS) 13 (PS)

 

CY-2014 Meetings

Note:

Documentation is organized by meeting month and day.

 

The relevant WBS is in parentheses - (6) means WBS 6 in our shorthand notation:

(SIT) indicates a Systems Integration Team meeting.

(CS) indicates a monthly Cost and Schedule Review.

(Engr) indicates a project-wide Engineering meeting.

(Matl) indicates a materials test meeting.

(CA) indicates a Critical Activities status meeting

(PS) indicates the weekly Project Status telecon

(CCB) indicates a Change Control Board meeting

(OFES) indicates a meeting with OFES.

(DC) indicates Dimensional Control

(OSF) indicates On-site Fabrication

(Weld) indicates a Weld Trials.

(PM) indicates weekly Project Manager meeting with entire project.

(PR) indicates a Project Review

(PS) indicates weekly status update

(WS) indicates a project workshop

 

January   
February  
March 21 (PS) 28 (PS)
April 03 (PS) 11 (PS) 17 (PS) 25 (PS)
May 01 (PS) 08 (PS) 15 (PS) 22 (PS) 30 (PS)
June

05 (PS) 13 (PS) 20 (PS) 27 (PS)

July 03 (PS) 11 (PS) 17 (PS) 25 (PS)
August 01 (PS)
September  
October  
November  
December  

Privacy and Security Notice

Please forward comments and questions to the Webmaster