Outstanding Action Items (last update 
1/20/2010)
Action: Neumeyer to update GRD to 
reflect latest revision. Due 1/5/10
Action: WBS Managers provide 
input for modification of FMEAs by 1/31 to C. Neumeyer.
Action: 
Ali to rerun OH Coil thermal with throttled flows to see 
if stresses can be reduced.
Status(1/6/2010): 
Latest analysis indicates stresses are at acceptable 
limits
Action: Dudek to meet with Mangra and 
Titus to work out need dates and priority list of 
items.
CLOSED (1/20/2010): 
Milestones submitted to P&C to track during 
statusing.
Action: Structural design criteria has a 
table with likelihood of failures that is in the NSTX (orig.) GRD. 
 Structural design criteria needs work to be released such as 
references Action: Titus to have it updated 
for approval and release
Action:  Inner PF Coils: CN needs to 
check if max volts / turn doesn't generate too much voltage on coils.  If 2 
kv or more may need addressing.
STATUS ( 1/20/10) CN still working
________________
Larry