Notes from 2/3 Meeting:

Strykowsky
Reviewed the milestones approaching the PDR in June.  Important dates to keep are WBS mgrs to deliver SRD's (draft) by 3/15,  SDD's (draft) by 4/30. See VGs 

Titus
Presented the latest analysis on the rib connection to the Vacuum Vessel, the welds and ribs are good to the PS limits.  Pete also presented the results of the OOP displacements of the OTF legs.  The displacements without any supports is approx. 8 cm.  Per Chrzanowski the existing spacing provided around the coils is only 1 inch (2.5 cm).  The design to limit for the leg deflections should be maintained at the current 1/4".  See VGs. 

Willard 
Presented a table showing the baseline flex connections versus the optimized design.   See VGs.

Viewgraphs will be posted by B. Simmons

http://nstx-upgrade.pppl.gov/Project_Meetings/CenterStackUpgrade/index_Meetings.htm

Outstanding Action Items (last update 2/3/2010)
Action: Neumeyer to update GRD to reflect latest revision. Due 2/5/10


Action: WBS Managers provide input for modification of FMEAs ASAP to C. Neumeyer.

Action: Structural design criteria has a table with likelihood of failures that is in the NSTX (orig.) GRD.  Structural design criteria needs work to be released such as references 
STATUS: Draft out for comment and review