NSTX NB2 TVPS (2485)
|
Name |
Begin date |
End date |
Duration |
Completion |
M & S |
Travel |
Basis |
Resources |
|
Conceptual Design
|
7/7/09
|
8/19/09
|
31
|
100
|
|
|
| |
|
CD of System Layout
|
7/7/09
|
8/4/09
|
20
|
100
|
|
|
| John Winkelman, Craig Priniski |
|
CD of Pump Duct(s)
|
8/4/09
|
8/11/09
|
5
|
100
|
|
|
| John Winkelman, Craig Priniski |
|
CD of Magnetic Shield
|
8/11/09
|
8/18/09
|
5
|
100
|
|
|
| Craig Priniski |
|
C&S Review
|
8/18/09
|
8/19/09
|
1
|
100
|
|
|
| Craig Priniski |
|
Prep for PPPL/Ext CDR
|
8/19/09
|
8/26/09
|
5
|
100
|
|
|
| Craig Priniski |
|
PPPL CDR
|
10/28/09
|
10/30/09
|
2
|
100
|
|
|
| John Winkelman, Craig Priniski |
|
Preliminary Design
|
10/30/09
|
6/1/10
|
152
|
100
|
|
|
| |
|
CDR Chit Resolution (all areas)
|
10/30/09
|
11/27/09
|
20
|
100
|
|
|
| John Winkelman, Craig Priniski |
|
FMEA Analysis
|
11/27/09
|
11/28/09
|
1
|
100
|
|
|
| Craig Priniski |
|
Preliminary CAD Designs
|
11/27/09
|
12/11/09
|
10
|
100
|
|
|
| John Winkelman, Craig Priniski |
|
Identify COTS Vendors
|
4/13/10
|
5/18/10
|
25
|
100
|
|
|
| Craig Priniski |
|
Update Cost & Schedule Estimate
|
4/19/10
|
4/22/10
|
3
|
100
|
|
|
| Craig Priniski |
|
Update CAD Models
|
5/18/10
|
6/1/10
|
10
|
100
|
|
|
| John Winkelman, Craig Priniski |
|
PDR Prep
|
6/1/10
|
6/15/10
|
10
|
100
|
|
|
| John Winkelman, Craig Priniski |
|
CONDUCT PDR
|
6/23/10
|
6/25/10
|
2
|
100
|
|
|
| |
|
Final Design
|
6/25/10
|
3/26/11
|
196
|
60
|
|
|
| |
|
Disposition PDR Chits
|
6/25/10
|
7/23/10
|
20
|
90
|
|
|
| John Winkelman, Craig Priniski |
|
Vacuum Diagnostic Layout
|
3/14/11
|
3/26/11
|
10
|
0
|
|
|
| John Winkelman, Craig Priniski |
|
Magnetic Shield Conceptual Design
|
10/1/10
|
11/12/10
|
30
|
100
|
|
|
| Craig Priniski, Larry Bryant |
|
Magnetic Shield Final Design
|
1/5/11
|
3/11/11
|
47
|
50
|
|
|
| John Winkelman, Craig Priniski, Larry Bryant |
|
Design Drawings
|
1/17/11
|
2/26/11
|
30
|
40
|
|
|
| John Winkelman, Craig Priniski |
|
Update Cost & Schedule Estimate
|
5/9/11
|
5/14/11
|
5
|
50
|
|
|
| Craig Priniski |
|
Peer Review
|
3/31/11
|
4/1/11
|
1
|
0
|
|
|
| |
|
FDR Prep
|
4/14/11
|
4/28/11
|
10
|
0
|
|
|
| John Winkelman, Craig Priniski |
|
CONDUCT FDR
|
6/15/11
|
6/16/11
|
1
|
0
|
|
|
| |
|
FDR Chit Resolution (all area)
|
6/16/11
|
7/14/11
|
20
|
0
|
|
|
| John Winkelman, Craig Priniski |
|
Procurement
|
7/14/11
|
3/14/14
|
696
|
0
|
|
|
| |
|
Item 1: 3200 l/s TMPs x 2
|
10/1/13
|
3/5/14
|
111
|
0
|
65
|
|
| |
|
Prep Requisition and procurement package Prep Requisition and procurement package
|
10/1/13
|
10/5/13
|
4
|
0
|
|
|
| Craig Priniski |
|
SUBMIT REQ TO PROCUREMENT
|
10/7/13
|
10/8/13
|
1
|
0
|
|
|
| Craig Priniski |
|
Procurement lead time
|
10/8/13
|
10/29/13
|
15
|
0
|
|
|
| |
|
AWARD
|
10/29/13
|
10/30/13
|
1
|
0
|
|
|
| |
|
Fabricate and delivery Fabricate or delivery
|
10/30/13
|
3/5/14
|
90
|
0
|
|
|
| |
|
Item 2: New VAT Valves (if needed)
|
10/7/13
|
2/21/14
|
99
|
0
|
22
|
|
| |
|
Prep Requisition and procurement package Prep Requisition and procurement package
|
10/7/13
|
10/9/13
|
2
|
0
|
|
|
| Craig Priniski |
|
SUBMIT REQ TO PROCUREMENT SUBMIT REQ TO PROCUREMENT
|
10/9/13
|
10/10/13
|
1
|
0
|
|
|
| |
|
Procurement lead time (1)
|
10/10/13
|
10/31/13
|
15
|
0
|
|
|
| |
|
AWARD
|
10/31/13
|
11/1/13
|
1
|
0
|
|
|
| |
|
Fabricate or delivery Fabricate or delivery
|
11/1/13
|
2/21/14
|
80
|
0
|
|
|
| |
|
Item 3: Vacuum Instimentation
|
10/10/13
|
3/14/14
|
111
|
0
|
5
|
|
| |
|
Prep Requisition and procurement package Prep Requisition and procurement package
|
10/10/13
|
10/16/13
|
4
|
0
|
|
|
| Craig Priniski |
|
SUBMIT REQ TO PROCUREMENT
|
10/16/13
|
10/17/13
|
1
|
0
|
|
|
| Craig Priniski |
|
Procurement lead time
|
10/17/13
|
11/7/13
|
15
|
0
|
|
|
| |
|
AWARD
|
11/7/13
|
11/8/13
|
1
|
0
|
|
|
| |
|
Fabricate for delivery
|
11/8/13
|
3/14/14
|
90
|
0
|
|
|
| |
|
Item 4: Ceramic Breaks for TMPs x 2
|
10/9/13
|
2/13/14
|
91
|
0
|
25
|
|
| |
|
Prep Requisition and procurement package Prep Requisition and procurement package
|
10/9/13
|
10/15/13
|
4
|
0
|
|
|
| Craig Priniski |
|
SUBMIT REQ TO PROCUREMENT SUBMIT REQ TO PROCUREMENT
|
10/15/13
|
10/16/13
|
1
|
0
|
|
|
| Craig Priniski |
|
Procurement lead time (1) Procurement lead time (1)
|
10/16/13
|
11/6/13
|
15
|
0
|
|
|
| |
|
AWARD
|
11/6/13
|
11/7/13
|
1
|
0
|
|
|
| |
|
Fabricate and delivery
|
11/7/13
|
2/13/14
|
70
|
0
|
|
|
| |
|
All other materials/compomnets for ducts
|
7/14/11
|
11/17/11
|
90
|
0
|
25
|
|
| Craig Priniski |
|
Installation Procedure
|
7/14/11
|
7/28/11
|
10
|
0
|
|
|
| Craig Priniski |
|
Outage Begin
|
8/29/12
|
8/30/12
|
1
|
0
|
|
|
| |
|
Installation
|
8/30/12
|
5/21/14
|
449
|
0
|
|
|
| |
|
Pre-Assemble Duct "Legs" 1 and 2
|
3/14/14
|
4/4/14
|
15
|
0
|
6
|
|
| Fabrication Tech #1, Craig Priniski, Fabrication Tech #2 |
|
Leak Checking
|
4/4/14
|
4/9/14
|
3
|
0
|
|
|
| Fabrication Tech #1 |
|
Install TVPS Supports/
|
8/30/12
|
9/11/12
|
8
|
0
|
|
|
| Fabrication Tech #1, Craig Priniski, Fabrication Tech #2 |
|
Install Ducts/Pumps
|
4/9/14
|
4/23/14
|
10
|
0
|
|
|
| Fabrication Tech #1, Craig Priniski, Fabrication Tech #2 |
|
Install Vac. Diagnostics
|
4/23/14
|
5/7/14
|
10
|
0
|
|
|
| Machine Tech, Craig Priniski |
|
PTP Testing
|
5/7/14
|
5/21/14
|
10
|
0
|
|
|
| Machine Tech, Craig Priniski |
|
Outage Ends
|
9/23/14
|
9/24/14
|
1
|
0
|
|
|
|
| Ganttproject (2.0.10) | ganttproject.biz
3/4/11 - 12:00:00 AM |