NSTX NB2 Duct & VV Mods

Name
Duration
Begin date
End date
Completion
M&S
Travel
Cost Basis
Resources
Conceptual Design
56
7/13/09
9/29/09
100
CD for NSTX VV in Bay J-K area
10
8/10/09
8/22/09
100
John Winkelman, Craig Priniski
CD of Port K Extension
3
8/24/09
8/27/09
100
John Winkelman, Craig Priniski
CD Ceramic Break Flanges
10
8/10/09
8/22/09
100
John Winkelman, Craig Priniski
CD Spool Piece
3
8/10/09
8/13/09
100
John Winkelman, Craig Priniski
C&S Development
10
7/13/09
7/25/09
100
Craig Priniski
C&S Review
1
7/27/09
7/28/09
100
Craig Priniski
NSTX J-K Mockup purchase
25
8/24/09
9/26/09
100
4
Craig Priniski
Prep for PPPL/Ext CDR
5
8/27/09
9/3/09
100
John Winkelman, Craig Priniski
PPPL CDR
1
9/28/09
9/29/09
100
John Winkelman, Craig Priniski
Preliminary Design
171
9/29/09
5/26/10
100
CDR Chit Resolution (all areas)
30
9/29/09
11/10/09
100
John Winkelman, Craig Priniski
FMEA Analysis
2
2/15/10
2/17/10
100
Craig Priniski
NSTX VV Modification Prototyping
60
2/18/10
5/13/10
100
6
John Winkelman, Craig Priniski, Tech-Fabrication
Update Cost & Schedule Estimate
18
3/23/10
4/16/10
100
Craig Priniski
Design Components
141
11/10/09
5/26/10
100
J-K Cap Weldment
45
11/10/09
1/12/10
100
John Winkelman, Craig Priniski
K-Port Extension
10
2/24/10
3/10/10
100
John Winkelman, Craig Priniski
NB-Ceramic Beak
7
1/15/10
1/26/10
100
John Winkelman, Craig Priniski
Spool Piece
10
1/26/10
2/9/10
100
John Winkelman, Craig Priniski
Round Bellows
10
2/9/10
2/23/10
100
John Winkelman, Craig Priniski
Rectangular Bellows
10
3/1/10
3/13/10
100
John Winkelman, Craig Priniski
Bay K/NB Duct Supports
59
2/9/10
5/1/10
100
Craig Priniski, Tech-Fabrication
J-K RWM Coil Redesign
32
4/12/10
5/26/10
100
New Layout/Supports
10
4/12/10
4/24/10
100
John Winkelman, Craig Priniski, George Labik
New Coil Components
22
4/26/10
5/26/10
100
John Winkelman, Craig Priniski, George Labik
NB Duct Thermal Shielding
25
4/19/10
5/22/10
100
John Winkelman, Craig Priniski
PDR Prep
43
4/15/10
6/15/10
100
John Winkelman, Craig Priniski
CONDUCT PDR
1
6/23/10
6/24/10
100
John Winkelman, Larry Bryant
Disposition PDR Chits
33
6/24/10
8/10/10
100
John Winkelman, Craig Priniski, Larry Bryant
Final Design
57
8/10/10
10/28/10
99
Seismic Analysis
5
8/10/10
8/17/10
100
Craig Priniski
K- Port Extension
7
10/4/10
10/13/10
100
John Winkelman, Craig Priniski
NB- Ceramic-Break
6
10/13/10
10/21/10
100
John Winkelman, Craig Priniski
Spool Piece/Round Bellows
5
10/21/10
10/28/10
100
John Winkelman, Craig Priniski
Retangular Bellows Assembly
5
10/21/10
10/28/10
95
John Winkelman, Craig Priniski
Installation Prototyping
70
12/13/10
3/19/11
40
Craig Priniski, Tech-Fabrication2, Tech-Fabrication
J-K Cap/Installation Procedure
24
3/21/11
4/22/11
30
John Winkelman, Craig Priniski
Design Drawings
39
2/21/11
4/15/11
95
John Winkelman, Craig Priniski
Update Analyses
155
8/10/10
3/15/11
90
Tom Willard, Craig Priniski
Update Cost & Schedule Estimate
7
5/30/11
6/8/11
60
Craig Priniski
Peer Review
1
3/31/11
4/1/11
0
FDR Prep
20
5/6/11
6/3/11
0
Craig Priniski, Larry Bryant
CONDUCT FDR
1
6/15/11
6/16/11
0
John Winkelman, Craig Priniski, Larry Bryant
Disposition FDR Chits
33
6/16/11
8/2/11
0
John Winkelman, Craig Priniski
Prep Procurement Specs (Early Action Items)
30
7/1/11
8/12/11
0
Craig Priniski
Procurement
508
7/5/11
6/14/13
0
Item 1: 40" VAT VALVES x2
234
8/15/11
7/6/12
0
250
SUBMIT REQ TO PROCUREMENT
1
5/28/12
5/29/12
0
Craig Priniski
Procurement lead time (1)
25
5/29/12
7/3/12
0
AWARD
3
7/3/12
7/6/12
0
Fabricate and Delivery
180
7/6/12
3/15/13
0
Item 2: 40" Bellows Section
160
8/22/11
3/31/12
0
200
6.0
SUBMIT REQ TO PROCUREMENT
1
8/22/11
8/23/11
0
Craig Priniski
Procurement lead time (1)
25
8/23/11
9/27/11
0
AWARD
3
9/27/11
9/30/11
0
Fabricate and Delivery
130
10/3/11
3/31/12
0
Item 3: Rectangular Bellows Section
480
8/12/11
6/14/13
0
400
6.0
SUBMIT REQ TO PROCUREMENT
1
8/12/11
8/13/11
0
Craig Priniski
Procurement lead time (1)
25
8/15/11
9/17/11
0
AWARD
1
12/1/11
12/2/11
0
Fabricate or delivery
400
12/2/11
6/14/13
0
Item 4: Vessel Cap & Port Extension
190
9/7/11
5/30/12
0
100
Prep Requisition and procurement package
8
2/1/12
2/11/12
0
Craig Priniski
SUBMIT REQ TO PROCUREMENT
1
2/13/12
2/14/12
0
Craig Priniski
Procurement lead time (1)
25
2/14/12
3/20/12
0
AWARD
1
4/19/12
4/20/12
0
Fabricate and delivery
190
4/20/12
1/11/13
0
Item 5: Spool Piece
120
7/5/11
12/20/11
0
40
3.0
Prep Requisition and procurement package
5
8/26/11
9/2/11
0
Craig Priniski
SUBMIT REQ TO PROCUREMENT
1
9/2/11
9/3/11
0
Procurement lead time (1)
25
9/5/11
10/8/11
0
AWARD
1
10/10/11
10/11/11
0
Fabricate or delivery
120
10/11/11
3/27/12
0
Item 6: RWM Coil Materials (copper)
60
10/4/12
12/27/12
0
12
Craig Priniski
Item 7: Raw materials for duct (added shield)
130
8/2/11
1/31/12
0
100
Prep Requisition and procurement package
3
8/2/11
8/5/11
0
Craig Priniski
SUBMIT REQ TO PROCUREMENT
1
8/5/11
8/6/11
0
Craig Priniski
Procurement lead time (1)
25
8/8/11
9/10/11
0
AWARD
1
9/12/11
9/13/11
0
Fabricate or delivery
100
9/13/11
1/31/12
0
Installation Procedure
60
1/16/12
4/7/12
0
Craig Priniski, Tech-Fabrication
OUTAGE BEGINES
1
3/30/12
3/31/12
0
Installation materials purchase
20
10/1/12
10/27/12
0
10
Installation
230
12/18/12
11/5/13
0
Duct Cladding Installation
10
3/6/13
3/20/13
0
Craig Priniski, Tech-Fabrication
J-K Vessel Modification
99
12/18/12
5/4/13
0
Install Vessel Supports/ Prep machine
12
12/18/12
1/3/13
0
5
Craig Priniski, Tech-Fabrication
Remove Bay-K Nozzel
8
1/7/13
1/17/13
0
Craig Priniski, Tech-Fabrication2, Tech-Fabrication
Cut J-K opening
30
1/17/13
2/28/13
0
Craig Priniski, Tech-Fabrication2, Tech-Fabrication
Fit Up/Install Cap
25
3/6/13
4/10/13
0
Craig Priniski, Tech-Fabrication2, Tech-Fabrication
Install Duct Supports
3
4/10/13
4/13/13
0
Craig Priniski, Tech-Fabrication2, Tech-Fabrication
Install K Extenstion
2
4/15/13
4/17/13
0
Craig Priniski, Tech-Fabrication
RWM Coil Installation
10
4/22/13
5/4/13
0
George Labik, Tech-Fabrication
NB2 Duct Construction
12
10/1/13
10/17/13
0
Make up NB2 Transition Duct
7
10/1/13
10/10/13
0
Craig Priniski, Tech-Fabrication2, Tech-Fabrication
Leak Check Duct
5
10/10/13
10/17/13
0
Tech-Fabrication2, Tech-Fabrication
Install Transition Duct
5
10/23/13
10/30/13
0
Craig Priniski, Tech-Fabrication2, Tech-Fabrication
Install, Connect Services
4
10/30/13
11/5/13
0
Tech-Fabrication2
Testing
5
11/5/13
11/12/13
0
Craig Priniski, Tech-Fabrication2
END OUTAGE
1
10/1/14
10/2/14
0