| NSTX NB2 Duct & VV Mods | 
| Name | Duration | Begin date | End date | Completion | M&S | Travel | Cost Basis | Resources | 
| Conceptual Design								 | 56 | 7/13/09 | 9/29/09 | 100 |  |  |  | |
| CD for NSTX VV in Bay J-K area | 10 | 8/10/09 | 8/22/09 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| CD of Port K Extension | 3 | 8/24/09 | 8/27/09 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| CD Ceramic Break Flanges | 10 | 8/10/09 | 8/22/09 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| CD Spool Piece | 3 | 8/10/09 | 8/13/09 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| C&S Development | 10 | 7/13/09 | 7/25/09 | 100 |  |  |  | Craig Priniski | 
| C&S Review | 1 | 7/27/09 | 7/28/09 | 100 |  |  |  | Craig Priniski | 
| NSTX J-K Mockup purchase | 25 | 8/24/09 | 9/26/09 | 100 | 4 |  |  | Craig Priniski | 
| Prep for PPPL/Ext CDR | 5 | 8/27/09 | 9/3/09 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| PPPL CDR | 1 | 9/28/09 | 9/29/09 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| Preliminary Design								 | 171 | 9/29/09 | 5/26/10 | 100 |  |  |  | |
| CDR Chit Resolution (all areas) | 30 | 9/29/09 | 11/10/09 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| FMEA Analysis | 2 | 2/15/10 | 2/17/10 | 100 |  |  |  | Craig Priniski | 
| NSTX VV Modification Prototyping | 60 | 2/18/10 | 5/13/10 | 100 | 6 |  |  | John Winkelman, Craig Priniski, Tech-Fabrication | 
| Update Cost & Schedule Estimate | 18 | 3/23/10 | 4/16/10 | 100 |  |  |  | Craig Priniski | 
| Design Components | 141 | 11/10/09 | 5/26/10 | 100 |  |  |  | |
| J-K Cap Weldment | 45 | 11/10/09 | 1/12/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| K-Port Extension | 10 | 2/24/10 | 3/10/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| NB-Ceramic Beak | 7 | 1/15/10 | 1/26/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| Spool Piece | 10 | 1/26/10 | 2/9/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| Round Bellows | 10 | 2/9/10 | 2/23/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| Rectangular Bellows | 10 | 3/1/10 | 3/13/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| Bay K/NB Duct Supports | 59 | 2/9/10 | 5/1/10 | 100 |  |  |  | Craig Priniski, Tech-Fabrication | 
| J-K RWM Coil Redesign								 | 32 | 4/12/10 | 5/26/10 | 100 |  |  |  | |
| New Layout/Supports | 10 | 4/12/10 | 4/24/10 | 100 |  |  |  | John Winkelman, Craig Priniski, George Labik | 
| New Coil Components | 22 | 4/26/10 | 5/26/10 | 100 |  |  |  | John Winkelman, Craig Priniski, George Labik | 
| NB Duct Thermal Shielding | 25 | 4/19/10 | 5/22/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| PDR Prep | 43 | 4/15/10 | 6/15/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| CONDUCT PDR | 1 | 6/23/10 | 6/24/10 | 100 |  |  |  | John Winkelman, Larry Bryant | 
| Disposition PDR Chits | 33 | 6/24/10 | 8/10/10 | 100 |  |  |  | John Winkelman, Craig Priniski, Larry Bryant | 
| Final Design								 | 57 | 8/10/10 | 10/28/10 | 99 |  |  |  | |
| Seismic Analysis | 5 | 8/10/10 | 8/17/10 | 100 |  |  |  | Craig Priniski | 
| K- Port Extension | 7 | 10/4/10 | 10/13/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| NB- Ceramic-Break | 6 | 10/13/10 | 10/21/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| Spool Piece/Round Bellows | 5 | 10/21/10 | 10/28/10 | 100 |  |  |  | John Winkelman, Craig Priniski | 
| Retangular Bellows Assembly | 5 | 10/21/10 | 10/28/10 | 95 |  |  |  | John Winkelman, Craig Priniski | 
| Installation Prototyping | 70 | 12/13/10 | 3/19/11 | 40 |  |  |  | Craig Priniski, Tech-Fabrication2, Tech-Fabrication | 
| J-K Cap/Installation Procedure | 24 | 3/21/11 | 4/22/11 | 30 |  |  |  | John Winkelman, Craig Priniski | 
| Design Drawings | 39 | 2/21/11 | 4/15/11 | 95 |  |  |  | John Winkelman, Craig Priniski | 
| Update Analyses | 155 | 8/10/10 | 3/15/11 | 90 |  |  |  | Tom Willard, Craig Priniski | 
| Update Cost & Schedule Estimate | 7 | 5/30/11 | 6/8/11 | 60 |  |  |  | Craig Priniski | 
| Peer Review | 1 | 3/31/11 | 4/1/11 | 0 |  |  |  | |
| FDR Prep | 20 | 5/6/11 | 6/3/11 | 0 |  |  |  | Craig Priniski, Larry Bryant | 
| CONDUCT FDR | 1 | 6/15/11 | 6/16/11 | 0 |  |  |  | John Winkelman, Craig Priniski, Larry Bryant | 
| Disposition FDR Chits | 33 | 6/16/11 | 8/2/11 | 0 |  |  |  | John Winkelman, Craig Priniski | 
| Prep Procurement Specs (Early Action Items) | 30 | 7/1/11 | 8/12/11 | 0 |  |  |  | Craig Priniski | 
| Procurement | 508 | 7/5/11 | 6/14/13 | 0 |  |  |  | |
| Item 1: 40" VAT VALVES x2 | 234 | 8/15/11 | 7/6/12 | 0 | 250 |  |  | |
| SUBMIT REQ TO PROCUREMENT | 1 | 5/28/12 | 5/29/12 | 0 |  |  |  | Craig Priniski | 
| Procurement lead time (1) | 25 | 5/29/12 | 7/3/12 | 0 |  |  |  | |
| AWARD | 3 | 7/3/12 | 7/6/12 | 0 |  |  |  | |
| Fabricate and Delivery | 180 | 7/6/12 | 3/15/13 | 0 |  |  |  | |
| Item 2: 40" Bellows Section | 160 | 8/22/11 | 3/31/12 | 0 | 200 | 6.0 |  | |
| SUBMIT REQ TO PROCUREMENT | 1 | 8/22/11 | 8/23/11 | 0 |  |  |  | Craig Priniski | 
| Procurement lead time (1) | 25 | 8/23/11 | 9/27/11 | 0 |  |  |  | |
| AWARD | 3 | 9/27/11 | 9/30/11 | 0 |  |  |  | |
| Fabricate and Delivery | 130 | 10/3/11 | 3/31/12 | 0 |  |  |  | |
| Item 3: Rectangular Bellows Section								 | 480 | 8/12/11 | 6/14/13 | 0 | 400 | 6.0 |  | |
| SUBMIT REQ TO PROCUREMENT | 1 | 8/12/11 | 8/13/11 | 0 |  |  |  | Craig Priniski | 
| Procurement lead time (1) | 25 | 8/15/11 | 9/17/11 | 0 |  |  |  | |
| AWARD | 1 | 12/1/11 | 12/2/11 | 0 |  |  |  | |
| Fabricate or delivery | 400 | 12/2/11 | 6/14/13 | 0 |  |  |  | |
| Item 4: Vessel Cap & Port Extension								 | 190 | 9/7/11 | 5/30/12 | 0 | 100 |  |  | |
| Prep Requisition and procurement package | 8 | 2/1/12 | 2/11/12 | 0 |  |  |  | Craig Priniski | 
| SUBMIT REQ TO PROCUREMENT | 1 | 2/13/12 | 2/14/12 | 0 |  |  |  | Craig Priniski | 
| Procurement lead time (1) | 25 | 2/14/12 | 3/20/12 | 0 |  |  |  | |
| AWARD | 1 | 4/19/12 | 4/20/12 | 0 |  |  |  | |
| Fabricate and delivery | 190 | 4/20/12 | 1/11/13 | 0 |  |  |  | |
| Item 5: Spool Piece								 | 120 | 7/5/11 | 12/20/11 | 0 | 40 | 3.0 |  | |
| Prep Requisition and procurement package | 5 | 8/26/11 | 9/2/11 | 0 |  |  |  | Craig Priniski | 
| SUBMIT REQ TO PROCUREMENT | 1 | 9/2/11 | 9/3/11 | 0 |  |  |  | |
| Procurement lead time (1) | 25 | 9/5/11 | 10/8/11 | 0 |  |  |  | |
| AWARD | 1 | 10/10/11 | 10/11/11 | 0 |  |  |  | |
| Fabricate or delivery | 120 | 10/11/11 | 3/27/12 | 0 |  |  |  | |
| Item 6: RWM Coil Materials (copper) | 60 | 10/4/12 | 12/27/12 | 0 | 12 |  |  | Craig Priniski | 
| Item 7: Raw materials for duct (added shield)								 | 130 | 8/2/11 | 1/31/12 | 0 | 100 |  |  | |
| Prep Requisition and procurement package | 3 | 8/2/11 | 8/5/11 | 0 |  |  |  | Craig Priniski | 
| SUBMIT REQ TO PROCUREMENT | 1 | 8/5/11 | 8/6/11 | 0 |  |  |  | Craig Priniski | 
| Procurement lead time (1) | 25 | 8/8/11 | 9/10/11 | 0 |  |  |  | |
| AWARD | 1 | 9/12/11 | 9/13/11 | 0 |  |  |  | |
| Fabricate or delivery | 100 | 9/13/11 | 1/31/12 | 0 |  |  |  | |
| Installation Procedure | 60 | 1/16/12 | 4/7/12 | 0 |  |  |  | Craig Priniski, Tech-Fabrication | 
| OUTAGE BEGINES | 1 | 3/30/12 | 3/31/12 | 0 |  |  |  | |
| Installation materials purchase | 20 | 10/1/12 | 10/27/12 | 0 | 10 |  |  | |
| Installation | 230 | 12/18/12 | 11/5/13 | 0 |  |  |  | |
| Duct Cladding Installation | 10 | 3/6/13 | 3/20/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication | 
| J-K Vessel Modification | 99 | 12/18/12 | 5/4/13 | 0 |  |  |  | |
| Install Vessel Supports/ Prep machine | 12 | 12/18/12 | 1/3/13 | 0 | 5 |  |  | Craig Priniski, Tech-Fabrication | 
| Remove Bay-K Nozzel | 8 | 1/7/13 | 1/17/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication2, Tech-Fabrication | 
| Cut J-K opening | 30 | 1/17/13 | 2/28/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication2, Tech-Fabrication | 
| Fit Up/Install Cap | 25 | 3/6/13 | 4/10/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication2, Tech-Fabrication | 
| Install Duct Supports | 3 | 4/10/13 | 4/13/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication2, Tech-Fabrication | 
| Install K Extenstion | 2 | 4/15/13 | 4/17/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication | 
| RWM Coil Installation | 10 | 4/22/13 | 5/4/13 | 0 |  |  |  | George Labik, Tech-Fabrication | 
| NB2 Duct Construction | 12 | 10/1/13 | 10/17/13 | 0 |  |  |  | |
| Make up NB2 Transition Duct | 7 | 10/1/13 | 10/10/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication2, Tech-Fabrication | 
| Leak Check Duct | 5 | 10/10/13 | 10/17/13 | 0 |  |  |  | Tech-Fabrication2, Tech-Fabrication | 
| Install Transition Duct | 5 | 10/23/13 | 10/30/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication2, Tech-Fabrication | 
| Install, Connect Services | 4 | 10/30/13 | 11/5/13 | 0 |  |  |  | Tech-Fabrication2 | 
| Testing | 5 | 11/5/13 | 11/12/13 | 0 |  |  |  | Craig Priniski, Tech-Fabrication2 | 
| END OUTAGE | 1 | 10/1/14 | 10/2/14 | 0 |  |  |  | 
| Ganttproject (2.0.10) | ganttproject.biz 3/4/11 - 12:00:00 AM |