NSTX NB2 Duct & VV Mods
|
Name |
Duration |
Begin date |
End date |
Completion |
M&S |
Travel |
Cost Basis |
Resources |
Conceptual Design
|
56
|
7/13/09
|
9/29/09
|
100
|
|
|
| |
CD for NSTX VV in Bay J-K area
|
10
|
8/10/09
|
8/22/09
|
100
|
|
|
| John Winkelman, Craig Priniski |
CD of Port K Extension
|
3
|
8/24/09
|
8/27/09
|
100
|
|
|
| John Winkelman, Craig Priniski |
CD Ceramic Break Flanges
|
10
|
8/10/09
|
8/22/09
|
100
|
|
|
| John Winkelman, Craig Priniski |
CD Spool Piece
|
3
|
8/10/09
|
8/13/09
|
100
|
|
|
| John Winkelman, Craig Priniski |
C&S Development
|
10
|
7/13/09
|
7/25/09
|
100
|
|
|
| Craig Priniski |
C&S Review
|
1
|
7/27/09
|
7/28/09
|
100
|
|
|
| Craig Priniski |
NSTX J-K Mockup purchase
|
25
|
8/24/09
|
9/26/09
|
100
|
4
|
|
| Craig Priniski |
Prep for PPPL/Ext CDR
|
5
|
8/27/09
|
9/3/09
|
100
|
|
|
| John Winkelman, Craig Priniski |
PPPL CDR
|
1
|
9/28/09
|
9/29/09
|
100
|
|
|
| John Winkelman, Craig Priniski |
Preliminary Design
|
171
|
9/29/09
|
5/26/10
|
100
|
|
|
| |
CDR Chit Resolution (all areas)
|
30
|
9/29/09
|
11/10/09
|
100
|
|
|
| John Winkelman, Craig Priniski |
FMEA Analysis
|
2
|
2/15/10
|
2/17/10
|
100
|
|
|
| Craig Priniski |
NSTX VV Modification Prototyping
|
60
|
2/18/10
|
5/13/10
|
100
|
6
|
|
| John Winkelman, Craig Priniski, Tech-Fabrication |
Update Cost & Schedule Estimate
|
18
|
3/23/10
|
4/16/10
|
100
|
|
|
| Craig Priniski |
Design Components
|
141
|
11/10/09
|
5/26/10
|
100
|
|
|
| |
J-K Cap Weldment
|
45
|
11/10/09
|
1/12/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
K-Port Extension
|
10
|
2/24/10
|
3/10/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
NB-Ceramic Beak
|
7
|
1/15/10
|
1/26/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
Spool Piece
|
10
|
1/26/10
|
2/9/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
Round Bellows
|
10
|
2/9/10
|
2/23/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
Rectangular Bellows
|
10
|
3/1/10
|
3/13/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
Bay K/NB Duct Supports
|
59
|
2/9/10
|
5/1/10
|
100
|
|
|
| Craig Priniski, Tech-Fabrication |
J-K RWM Coil Redesign
|
32
|
4/12/10
|
5/26/10
|
100
|
|
|
| |
New Layout/Supports
|
10
|
4/12/10
|
4/24/10
|
100
|
|
|
| John Winkelman, Craig Priniski, George Labik |
New Coil Components
|
22
|
4/26/10
|
5/26/10
|
100
|
|
|
| John Winkelman, Craig Priniski, George Labik |
NB Duct Thermal Shielding
|
25
|
4/19/10
|
5/22/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
PDR Prep
|
43
|
4/15/10
|
6/15/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
CONDUCT PDR
|
1
|
6/23/10
|
6/24/10
|
100
|
|
|
| John Winkelman, Larry Bryant |
Disposition PDR Chits
|
33
|
6/24/10
|
8/10/10
|
100
|
|
|
| John Winkelman, Craig Priniski, Larry Bryant |
Final Design
|
57
|
8/10/10
|
10/28/10
|
99
|
|
|
| |
Seismic Analysis
|
5
|
8/10/10
|
8/17/10
|
100
|
|
|
| Craig Priniski |
K- Port Extension
|
7
|
10/4/10
|
10/13/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
NB- Ceramic-Break
|
6
|
10/13/10
|
10/21/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
Spool Piece/Round Bellows
|
5
|
10/21/10
|
10/28/10
|
100
|
|
|
| John Winkelman, Craig Priniski |
Retangular Bellows Assembly
|
5
|
10/21/10
|
10/28/10
|
95
|
|
|
| John Winkelman, Craig Priniski |
Installation Prototyping
|
70
|
12/13/10
|
3/19/11
|
40
|
|
|
| Craig Priniski, Tech-Fabrication2, Tech-Fabrication |
J-K Cap/Installation Procedure
|
24
|
3/21/11
|
4/22/11
|
30
|
|
|
| John Winkelman, Craig Priniski |
Design Drawings
|
39
|
2/21/11
|
4/15/11
|
95
|
|
|
| John Winkelman, Craig Priniski |
Update Analyses
|
155
|
8/10/10
|
3/15/11
|
90
|
|
|
| Tom Willard, Craig Priniski |
Update Cost & Schedule Estimate
|
7
|
5/30/11
|
6/8/11
|
60
|
|
|
| Craig Priniski |
Peer Review
|
1
|
3/31/11
|
4/1/11
|
0
|
|
|
| |
FDR Prep
|
20
|
5/6/11
|
6/3/11
|
0
|
|
|
| Craig Priniski, Larry Bryant |
CONDUCT FDR
|
1
|
6/15/11
|
6/16/11
|
0
|
|
|
| John Winkelman, Craig Priniski, Larry Bryant |
Disposition FDR Chits
|
33
|
6/16/11
|
8/2/11
|
0
|
|
|
| John Winkelman, Craig Priniski |
Prep Procurement Specs (Early Action Items)
|
30
|
7/1/11
|
8/12/11
|
0
|
|
|
| Craig Priniski |
Procurement
|
508
|
7/5/11
|
6/14/13
|
0
|
|
|
| |
Item 1: 40" VAT VALVES x2
|
234
|
8/15/11
|
7/6/12
|
0
|
250
|
|
| |
SUBMIT REQ TO PROCUREMENT
|
1
|
5/28/12
|
5/29/12
|
0
|
|
|
| Craig Priniski |
Procurement lead time (1)
|
25
|
5/29/12
|
7/3/12
|
0
|
|
|
| |
AWARD
|
3
|
7/3/12
|
7/6/12
|
0
|
|
|
| |
Fabricate and Delivery
|
180
|
7/6/12
|
3/15/13
|
0
|
|
|
| |
Item 2: 40" Bellows Section
|
160
|
8/22/11
|
3/31/12
|
0
|
200
|
6.0
|
| |
SUBMIT REQ TO PROCUREMENT
|
1
|
8/22/11
|
8/23/11
|
0
|
|
|
| Craig Priniski |
Procurement lead time (1)
|
25
|
8/23/11
|
9/27/11
|
0
|
|
|
| |
AWARD
|
3
|
9/27/11
|
9/30/11
|
0
|
|
|
| |
Fabricate and Delivery
|
130
|
10/3/11
|
3/31/12
|
0
|
|
|
| |
Item 3: Rectangular Bellows Section
|
480
|
8/12/11
|
6/14/13
|
0
|
400
|
6.0
|
| |
SUBMIT REQ TO PROCUREMENT
|
1
|
8/12/11
|
8/13/11
|
0
|
|
|
| Craig Priniski |
Procurement lead time (1)
|
25
|
8/15/11
|
9/17/11
|
0
|
|
|
| |
AWARD
|
1
|
12/1/11
|
12/2/11
|
0
|
|
|
| |
Fabricate or delivery
|
400
|
12/2/11
|
6/14/13
|
0
|
|
|
| |
Item 4: Vessel Cap & Port Extension
|
190
|
9/7/11
|
5/30/12
|
0
|
100
|
|
| |
Prep Requisition and procurement package
|
8
|
2/1/12
|
2/11/12
|
0
|
|
|
| Craig Priniski |
SUBMIT REQ TO PROCUREMENT
|
1
|
2/13/12
|
2/14/12
|
0
|
|
|
| Craig Priniski |
Procurement lead time (1)
|
25
|
2/14/12
|
3/20/12
|
0
|
|
|
| |
AWARD
|
1
|
4/19/12
|
4/20/12
|
0
|
|
|
| |
Fabricate and delivery
|
190
|
4/20/12
|
1/11/13
|
0
|
|
|
| |
Item 5: Spool Piece
|
120
|
7/5/11
|
12/20/11
|
0
|
40
|
3.0
|
| |
Prep Requisition and procurement package
|
5
|
8/26/11
|
9/2/11
|
0
|
|
|
| Craig Priniski |
SUBMIT REQ TO PROCUREMENT
|
1
|
9/2/11
|
9/3/11
|
0
|
|
|
| |
Procurement lead time (1)
|
25
|
9/5/11
|
10/8/11
|
0
|
|
|
| |
AWARD
|
1
|
10/10/11
|
10/11/11
|
0
|
|
|
| |
Fabricate or delivery
|
120
|
10/11/11
|
3/27/12
|
0
|
|
|
| |
Item 6: RWM Coil Materials (copper)
|
60
|
10/4/12
|
12/27/12
|
0
|
12
|
|
| Craig Priniski |
Item 7: Raw materials for duct (added shield)
|
130
|
8/2/11
|
1/31/12
|
0
|
100
|
|
| |
Prep Requisition and procurement package
|
3
|
8/2/11
|
8/5/11
|
0
|
|
|
| Craig Priniski |
SUBMIT REQ TO PROCUREMENT
|
1
|
8/5/11
|
8/6/11
|
0
|
|
|
| Craig Priniski |
Procurement lead time (1)
|
25
|
8/8/11
|
9/10/11
|
0
|
|
|
| |
AWARD
|
1
|
9/12/11
|
9/13/11
|
0
|
|
|
| |
Fabricate or delivery
|
100
|
9/13/11
|
1/31/12
|
0
|
|
|
| |
Installation Procedure
|
60
|
1/16/12
|
4/7/12
|
0
|
|
|
| Craig Priniski, Tech-Fabrication |
OUTAGE BEGINES
|
1
|
3/30/12
|
3/31/12
|
0
|
|
|
| |
Installation materials purchase
|
20
|
10/1/12
|
10/27/12
|
0
|
10
|
|
| |
Installation
|
230
|
12/18/12
|
11/5/13
|
0
|
|
|
| |
Duct Cladding Installation
|
10
|
3/6/13
|
3/20/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication |
J-K Vessel Modification
|
99
|
12/18/12
|
5/4/13
|
0
|
|
|
| |
Install Vessel Supports/ Prep machine
|
12
|
12/18/12
|
1/3/13
|
0
|
5
|
|
| Craig Priniski, Tech-Fabrication |
Remove Bay-K Nozzel
|
8
|
1/7/13
|
1/17/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication2, Tech-Fabrication |
Cut J-K opening
|
30
|
1/17/13
|
2/28/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication2, Tech-Fabrication |
Fit Up/Install Cap
|
25
|
3/6/13
|
4/10/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication2, Tech-Fabrication |
Install Duct Supports
|
3
|
4/10/13
|
4/13/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication2, Tech-Fabrication |
Install K Extenstion
|
2
|
4/15/13
|
4/17/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication |
RWM Coil Installation
|
10
|
4/22/13
|
5/4/13
|
0
|
|
|
| George Labik, Tech-Fabrication |
NB2 Duct Construction
|
12
|
10/1/13
|
10/17/13
|
0
|
|
|
| |
Make up NB2 Transition Duct
|
7
|
10/1/13
|
10/10/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication2, Tech-Fabrication |
Leak Check Duct
|
5
|
10/10/13
|
10/17/13
|
0
|
|
|
| Tech-Fabrication2, Tech-Fabrication |
Install Transition Duct
|
5
|
10/23/13
|
10/30/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication2, Tech-Fabrication |
Install, Connect Services
|
4
|
10/30/13
|
11/5/13
|
0
|
|
|
| Tech-Fabrication2 |
Testing
|
5
|
11/5/13
|
11/12/13
|
0
|
|
|
| Craig Priniski, Tech-Fabrication2 |
END OUTAGE
|
1
|
10/1/14
|
10/2/14
|
0
|
|
|
|
Ganttproject (2.0.10) | ganttproject.biz
3/4/11 - 12:00:00 AM |