NB2 Upgrade Armor

Name
Begin date
End date
Duration
Completion
M&S
Travel
Coordinator
Resources
Conceptual Design
8/10/09
9/29/09
36
100
Armor Layout
8/10/09
8/15/09
5
100
Craig Priniski
Craig Priniski, John Winkelman
Thermal Annalysis of Second Beam
8/17/09
8/29/09
10
100
Kelsey Tresemer
Kelsey Tresemer, John Winkelman
CD of Supports and plates
8/17/09
9/5/09
15
100
Craig Priniski
Craig Priniski, John Winkelman
Tile modifications
8/31/09
9/12/09
10
100
Kelsey Tresemer
Kelsey Tresemer, John Winkelman
Bay H Port Cover Design
9/15/09
9/29/09
10
100
Craig Priniski
Craig Priniski, John Winkelman
CDR Prep
9/29/09
10/9/09
8
100
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski, John Winkelman
PPPL CDR
10/28/09
10/30/09
2
100
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski, John Winkelman
Preliminary Design
10/30/09
6/17/10
164
100
CDR Chit Resolution
10/30/09
12/11/09
30
100
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski, John Winkelman
Design Components
12/15/09
5/19/10
111
100
New Support Design
1/11/10
3/20/10
50
100
Craig Priniski
Kelsey Tresemer, Craig Priniski, John Winkelman
Tile Themal Modeling
12/15/09
2/24/10
51
100
Kelsey Tresemer
Kelsey Tresemer
Tile Material Selection
2/24/10
5/19/10
60
100
Kelsey Tresemer
Kelsey Tresemer
MSE-LIF Integration
12/11/09
1/22/10
30
100
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski, John Winkelman
Armor E-Mag Analysis
4/12/10
4/29/10
13
100
Kelsey Tresemer
Kelsey Tresemer, Larry Bryant
Armor Thermal Analysys
4/29/10
6/3/10
25
100
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski, Larry Bryant
Support Hardware Design
6/3/10
6/17/10
10
100
Craig Priniski
Craig Priniski, John Winkelman
Update Cost & Schedule Estimate
4/14/10
4/20/10
4
100
Craig Priniski
Kelsey Tresemer, Craig Priniski
PDR Prep
6/17/10
6/24/10
5
100
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski, John Winkelman
CONDUCT PDR
6/24/10
6/26/10
2
100
Kelsey Tresemer
Kelsey Tresemer
Final Design
6/28/10
4/12/11
206
59
Disposition PDR Chits
6/28/10
7/24/10
20
100
Kelsey Tresemer
Kelsey Tresemer, John Winkelman
Revise Armor Backing
6/28/10
7/24/10
20
100
Craig Priniski
Kelsey Tresemer, Craig Priniski, John Winkelman
Design Drawings
9/27/10
11/6/10
30
100
Kelsey Tresemer
Kelsey Tresemer, John Winkelman
Armor Instrumentation (thermocouples)
1/27/11
2/24/11
20
50
Craig Priniski
Kelsey Tresemer, Craig Priniski, John Winkelman
Develope Instalation Techniques
3/15/11
4/12/11
20
0
Craig Priniski
Kelsey Tresemer, Craig Priniski, John Winkelman
Update Analysis
2/25/11
4/8/11
30
10
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski
Update Cost & Schedule
5/30/11
6/7/11
6
40
Craig Priniski
Craig Priniski
Peer Review
3/31/11
4/1/11
1
0
FDR Prep
4/28/11
5/26/11
20
0
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski, John Winkelman, Larry Bryant
CONDUCT FDR
6/15/11
6/16/11
1
0
FDR Chit Resolution
6/16/11
7/14/11
20
0
Larry Bryant
Kelsey Tresemer, Craig Priniski, John Winkelman, Larry Bryant
Procurment Action
6/4/12
11/23/13
385
0
Item 1: Armor Tiles, CFCs
6/4/12
6/8/13
265
0
95
5
Prep Requisition and procurement package
6/4/12
6/16/12
10
0
Kelsey Tresemer
Kelsey Tresemer
SUBMIT REQ TO PROCUREMENT
6/18/12
6/19/12
1
0
Kelsey Tresemer
Procurement lead time (1)
6/19/12
8/14/12
40
0
AWARD
8/14/12
8/15/12
1
0
Kelsey Tresemer
Kelsey Tresemer
Fabricate for delivery
10/1/12
6/8/13
180
0
Item 2: Bay-H Port Cover - Armor Suppotts
3/1/13
11/23/13
191
0
45
Prep Requisition and procurement package
3/1/13
3/15/13
10
0
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski
SUBMIT REQ TO PROCUREMENT
3/15/13
3/16/13
1
0
Kelsey Tresemer
Kelsey Tresemer
Procurement lead time (1)
3/18/13
4/20/13
25
0
AWARD
4/22/13
4/23/13
1
0
Fabricate for delivery
9/2/13
11/23/13
60
0
Item 3: New Backing Plates
9/4/12
10/27/12
39
0
20
Prep Requisition and procurement package
9/4/12
9/6/12
2
0
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski
SUBMIT REQ TO PROCUREMENT
9/6/12
9/7/12
1
0
Kelsey Tresemer
Kelsey Tresemer
Procurement lead time (1)
9/7/12
9/28/12
15
0
AWARD
9/28/12
9/29/12
1
0
Delivery
10/1/12
10/27/12
20
0
Outage Begins
8/29/12
8/30/12
1
0
Fabricate Backing Plates
10/29/12
11/17/12
15
0
Craig Priniski
Craig Priniski, Fabrication Tech #2, Fabrication Tech #1
Pre-Assemble Armor
6/10/13
7/10/13
22
0
Assemble Armmor Quad #1
6/10/13
6/19/13
7
0
Fabrication Tech #1
Fabrication Tech #2, Fabrication Tech #1
Assemble Armmor Quad #2
6/19/13
6/26/13
5
0
Fabrication Tech #1
Fabrication Tech #2, Fabrication Tech #1
Assemble Armmor Quad #3
6/26/13
7/3/13
5
0
Fabrication Tech #1
Fabrication Tech #2, Fabrication Tech #1
net.sourceforge.ganttproject.delay.Delay@1930611
7/3/13
7/10/13
5
0
Fabrication Tech #1
Fabrication Tech #2, Fabrication Tech #1
Assembly Procedure Finalized
6/28/13
7/19/13
15
0
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski
Installation
8/30/12
1/10/14
356
0
In Vessel Work Remove Armor
8/30/12
9/27/12
20
0
Machine Tech #1
Machine Tech #1, Fabrication Tech #1
Armor Support Installation
11/25/13
12/7/13
10
0
8
Kelsey Tresemer
Machine Tech #1, Kelsey Tresemer, Fabrication Tech #1
Armor Quadrent Instalations
12/9/13
12/28/13
15
0
Fabrication Tech #1
Machine Tech #1, Craig Priniski, Fabrication Tech #1
Sevice Connections
12/30/13
1/3/14
4
0
Machine Tech #1
Machine Tech #1, Fabrication Tech #1
Bay-H Port Cover Install
1/3/14
1/8/14
3
0
Craig Priniski
Machine Tech #1, Craig Priniski, Fabrication Tech #1
Testing
1/8/14
1/10/14
2
0
Craig Priniski
Machine Tech #1, Craig Priniski
Outage Ends
10/1/14
10/2/14
1
0

Ganttproject (2.0.10)ganttproject.biz
3/4/11 - 12:00:00 AM