| NB2 Upgrade Armor | 
| Name | Begin date | End date | Duration | Completion | M&S | Travel | Coordinator | Resources | 
| Conceptual Design	 | 8/10/09 | 9/29/09 | 36 | 100 |  |  | ||
| Armor Layout | 8/10/09 | 8/15/09 | 5 | 100 |  |  | Craig Priniski | Craig Priniski, John Winkelman | 
| Thermal Annalysis of Second Beam | 8/17/09 | 8/29/09 | 10 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, John Winkelman | 
| CD of Supports and plates | 8/17/09 | 9/5/09 | 15 | 100 |  |  | Craig Priniski | Craig Priniski, John Winkelman | 
| Tile modifications | 8/31/09 | 9/12/09 | 10 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, John Winkelman | 
| Bay H Port Cover Design | 9/15/09 | 9/29/09 | 10 | 100 |  |  | Craig Priniski | Craig Priniski, John Winkelman | 
| CDR Prep | 9/29/09 | 10/9/09 | 8 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| PPPL CDR | 10/28/09 | 10/30/09 | 2 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| Preliminary Design	 | 10/30/09 | 6/17/10 | 164 | 100 |  |  | ||
| CDR Chit Resolution | 10/30/09 | 12/11/09 | 30 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| Design Components	 | 12/15/09 | 5/19/10 | 111 | 100 |  |  | ||
| New Support Design | 1/11/10 | 3/20/10 | 50 | 100 |  |  | Craig Priniski | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| Tile Themal Modeling | 12/15/09 | 2/24/10 | 51 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer | 
| Tile Material Selection | 2/24/10 | 5/19/10 | 60 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer | 
| MSE-LIF Integration | 12/11/09 | 1/22/10 | 30 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| Armor E-Mag Analysis | 4/12/10 | 4/29/10 | 13 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, Larry Bryant | 
| Armor Thermal Analysys | 4/29/10 | 6/3/10 | 25 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski, Larry Bryant | 
| Support Hardware Design | 6/3/10 | 6/17/10 | 10 | 100 |  |  | Craig Priniski | Craig Priniski, John Winkelman | 
| Update Cost & Schedule Estimate | 4/14/10 | 4/20/10 | 4 | 100 |  |  | Craig Priniski | Kelsey Tresemer, Craig Priniski | 
| PDR Prep | 6/17/10 | 6/24/10 | 5 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| CONDUCT PDR | 6/24/10 | 6/26/10 | 2 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer | 
| Final Design	 | 6/28/10 | 4/12/11 | 206 | 59 |  |  | ||
| Disposition PDR Chits | 6/28/10 | 7/24/10 | 20 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, John Winkelman | 
| Revise Armor Backing | 6/28/10 | 7/24/10 | 20 | 100 |  |  | Craig Priniski | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| Design Drawings | 9/27/10 | 11/6/10 | 30 | 100 |  |  | Kelsey Tresemer | Kelsey Tresemer, John Winkelman | 
| Armor Instrumentation (thermocouples) | 1/27/11 | 2/24/11 | 20 | 50 |  |  | Craig Priniski | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| Develope Instalation Techniques | 3/15/11 | 4/12/11 | 20 | 0 |  |  | Craig Priniski | Kelsey Tresemer, Craig Priniski, John Winkelman | 
| Update Analysis | 2/25/11 | 4/8/11 | 30 | 10 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski | 
| Update Cost & Schedule | 5/30/11 | 6/7/11 | 6 | 40 |  |  | Craig Priniski | Craig Priniski | 
| Peer Review | 3/31/11 | 4/1/11 | 1 | 0 |  |  | ||
| FDR Prep | 4/28/11 | 5/26/11 | 20 | 0 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski, John Winkelman, Larry Bryant | 
| CONDUCT FDR | 6/15/11 | 6/16/11 | 1 | 0 |  |  | ||
| FDR Chit Resolution | 6/16/11 | 7/14/11 | 20 | 0 |  |  | Larry Bryant | Kelsey Tresemer, Craig Priniski, John Winkelman, Larry Bryant | 
| Procurment Action | 6/4/12 | 11/23/13 | 385 | 0 |  |  | ||
| Item 1: Armor Tiles, CFCs	 | 6/4/12 | 6/8/13 | 265 | 0 | 95 | 5 | ||
| Prep Requisition and procurement package | 6/4/12 | 6/16/12 | 10 | 0 |  |  | Kelsey Tresemer | Kelsey Tresemer | 
| SUBMIT REQ TO PROCUREMENT | 6/18/12 | 6/19/12 | 1 | 0 |  |  | Kelsey Tresemer | |
| Procurement lead time (1) | 6/19/12 | 8/14/12 | 40 | 0 |  |  | ||
| AWARD | 8/14/12 | 8/15/12 | 1 | 0 |  |  | Kelsey Tresemer | Kelsey Tresemer | 
| Fabricate for delivery | 10/1/12 | 6/8/13 | 180 | 0 |  |  | ||
| Item 2: Bay-H Port Cover - Armor Suppotts | 3/1/13 | 11/23/13 | 191 | 0 | 45 |  | ||
| Prep Requisition and procurement package | 3/1/13 | 3/15/13 | 10 | 0 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski | 
| SUBMIT REQ TO PROCUREMENT | 3/15/13 | 3/16/13 | 1 | 0 |  |  | Kelsey Tresemer | Kelsey Tresemer | 
| Procurement lead time (1) | 3/18/13 | 4/20/13 | 25 | 0 |  |  | ||
| AWARD | 4/22/13 | 4/23/13 | 1 | 0 |  |  | ||
| Fabricate for delivery | 9/2/13 | 11/23/13 | 60 | 0 |  |  | ||
| Item 3: New Backing Plates	 | 9/4/12 | 10/27/12 | 39 | 0 | 20 |  | ||
| Prep Requisition and procurement package | 9/4/12 | 9/6/12 | 2 | 0 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski | 
| SUBMIT REQ TO PROCUREMENT | 9/6/12 | 9/7/12 | 1 | 0 |  |  | Kelsey Tresemer | Kelsey Tresemer | 
| Procurement lead time (1) | 9/7/12 | 9/28/12 | 15 | 0 |  |  | ||
| AWARD | 9/28/12 | 9/29/12 | 1 | 0 |  |  | ||
| Delivery | 10/1/12 | 10/27/12 | 20 | 0 |  |  | ||
| Outage Begins | 8/29/12 | 8/30/12 | 1 | 0 |  |  | ||
| Fabricate Backing Plates | 10/29/12 | 11/17/12 | 15 | 0 |  |  | Craig Priniski | Craig Priniski, Fabrication Tech #2, Fabrication Tech #1 | 
| Pre-Assemble Armor | 6/10/13 | 7/10/13 | 22 | 0 |  |  | ||
| Assemble Armmor Quad #1 | 6/10/13 | 6/19/13 | 7 | 0 |  |  | Fabrication Tech #1 | Fabrication Tech #2, Fabrication Tech #1 | 
| Assemble Armmor Quad #2 | 6/19/13 | 6/26/13 | 5 | 0 |  |  | Fabrication Tech #1 | Fabrication Tech #2, Fabrication Tech #1 | 
| Assemble Armmor Quad #3 | 6/26/13 | 7/3/13 | 5 | 0 |  |  | Fabrication Tech #1 | Fabrication Tech #2, Fabrication Tech #1 | 
| net.sourceforge.ganttproject.delay.Delay@1930611 | 7/3/13 | 7/10/13 | 5 | 0 |  |  | Fabrication Tech #1 | Fabrication Tech #2, Fabrication Tech #1 | 
| Assembly Procedure Finalized | 6/28/13 | 7/19/13 | 15 | 0 |  |  | Kelsey Tresemer | Kelsey Tresemer, Craig Priniski | 
| Installation | 8/30/12 | 1/10/14 | 356 | 0 |  |  | ||
| In Vessel Work Remove Armor | 8/30/12 | 9/27/12 | 20 | 0 |  |  | Machine Tech #1 | Machine Tech #1, Fabrication Tech #1 | 
| Armor Support Installation | 11/25/13 | 12/7/13 | 10 | 0 | 8 |  | Kelsey Tresemer | Machine Tech #1, Kelsey Tresemer, Fabrication Tech #1 | 
| Armor Quadrent Instalations | 12/9/13 | 12/28/13 | 15 | 0 |  |  | Fabrication Tech #1 | Machine Tech #1, Craig Priniski, Fabrication Tech #1 | 
| Sevice Connections | 12/30/13 | 1/3/14 | 4 | 0 |  |  | Machine Tech #1 | Machine Tech #1, Fabrication Tech #1 | 
| Bay-H Port Cover Install | 1/3/14 | 1/8/14 | 3 | 0 |  |  | Craig Priniski | Machine Tech #1, Craig Priniski, Fabrication Tech #1 | 
| Testing | 1/8/14 | 1/10/14 | 2 | 0 |  |  | Craig Priniski | Machine Tech #1, Craig Priniski | 
| Outage Ends | 10/1/14 | 10/2/14 | 1 | 0 |  |  | 