NB2 Upgrade Armor

Name
Begin date
End date
Duration
Completion
M&S
Travel
Coordinator
Resources
Conceptual Design
8/10/09
9/29/09
36
100
Armor Layout
8/10/09
8/15/09
5
100
Craig Priniski
John Winkelman, Craig Priniski
Thermal Annalysis of Second Beam
8/17/09
8/29/09
10
100
Kelsey Tresemer
John Winkelman, Kelsey Tresemer
CD of Supports and plates
8/17/09
9/5/09
15
100
Craig Priniski
John Winkelman, Craig Priniski
Tile modifications
8/31/09
9/12/09
10
100
Kelsey Tresemer
John Winkelman, Kelsey Tresemer
Bay H Port Cover Design
9/15/09
9/29/09
10
100
Craig Priniski
John Winkelman, Craig Priniski
CDR Prep
9/29/09
10/9/09
8
100
Kelsey Tresemer
John Winkelman, Kelsey Tresemer, Craig Priniski
PPPL CDR
10/28/09
10/30/09
2
100
Kelsey Tresemer
John Winkelman, Kelsey Tresemer, Craig Priniski
Preliminary Design
10/30/09
6/17/10
164
100
CDR Chit Resolution
10/30/09
12/11/09
30
100
Kelsey Tresemer
John Winkelman, Kelsey Tresemer, Craig Priniski
Design Components
12/15/09
5/19/10
111
100
New Support Design
1/11/10
3/20/10
50
100
Craig Priniski
John Winkelman, Kelsey Tresemer, Craig Priniski
Tile Themal Modeling
12/15/09
2/24/10
51
100
Kelsey Tresemer
Kelsey Tresemer
Tile Material Selection
2/24/10
5/19/10
60
100
Kelsey Tresemer
Kelsey Tresemer
MSE-LIF Integration
12/11/09
1/22/10
30
100
Kelsey Tresemer
John Winkelman, Kelsey Tresemer, Craig Priniski
Armor E-Mag Analysis
4/12/10
4/29/10
13
100
Kelsey Tresemer
Kelsey Tresemer, Larry Bryant
Armor Thermal Analysys
4/29/10
6/3/10
25
100
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski, Larry Bryant
Support Hardware Design
6/3/10
6/17/10
10
100
Craig Priniski
John Winkelman, Craig Priniski
Update Cost & Schedule Estimate
4/14/10
4/20/10
4
100
Craig Priniski
Kelsey Tresemer, Craig Priniski
PDR Prep
6/17/10
6/24/10
5
100
Kelsey Tresemer
John Winkelman, Kelsey Tresemer, Craig Priniski
CONDUCT PDR
6/24/10
6/26/10
2
100
Kelsey Tresemer
Kelsey Tresemer
Final Design
6/28/10
1/13/11
143
31
Disposition PDR Chits
6/28/10
7/24/10
20
100
Kelsey Tresemer
John Winkelman, Kelsey Tresemer
Revise Armor Backing
6/28/10
7/24/10
20
100
Craig Priniski
John Winkelman, Kelsey Tresemer, Craig Priniski
Design Drawings
8/2/10
9/11/10
30
58
Kelsey Tresemer
John Winkelman, Kelsey Tresemer
Tile Material Evanluation
10/7/10
12/2/10
40
0
6
3
Kelsey Tresemer
Kelsey Tresemer, Fabrication Tech #1
Armor Instrumentation (thermocouples)
11/18/10
12/2/10
10
0
Craig Priniski
John Winkelman, Kelsey Tresemer, Craig Priniski
Develope Instalation Techniques
12/2/10
12/30/10
20
0
Craig Priniski
John Winkelman, Kelsey Tresemer, Craig Priniski
Update Analysis
12/2/10
1/13/11
30
0
Kelsey Tresemer
Kelsey Tresemer, Larry Bryant
Update Cost & Schedule
1/13/11
1/19/11
4
0
Craig Priniski
Kelsey Tresemer, Craig Priniski
FDR Prep
1/19/11
2/16/11
20
0
Kelsey Tresemer
John Winkelman, Kelsey Tresemer, Craig Priniski, Larry Bryant
CONDUCT FDR
3/28/11
3/29/11
1
0
FDR Chit Resolution
3/29/11
4/26/11
20
0
Larry Bryant
John Winkelman, Kelsey Tresemer, Craig Priniski, Larry Bryant
Procurment Action
4/26/11
2/13/13
471
0
Item 1: Armor Tiles, CFCs
4/26/11
7/5/12
312
0
95
Prep Requisition and procurement package
4/26/11
5/10/11
10
0
Kelsey Tresemer
Kelsey Tresemer
SUBMIT REQ TO PROCUREMENT
5/10/11
5/11/11
1
0
Kelsey Tresemer
Procurement lead time (1)
5/11/11
7/6/11
40
0
AWARD
7/6/11
7/7/11
1
0
Kelsey Tresemer
Kelsey Tresemer
Fabricate for delivery
7/7/11
7/5/12
260
0
Item 2: Bay-H Port Cover - Armor Suppotts
10/1/12
2/13/13
97
0
45
Prep Requisition and procurement package
5/10/11
5/24/11
10
0
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski
SUBMIT REQ TO PROCUREMENT
5/24/11
5/25/11
1
0
Kelsey Tresemer
Kelsey Tresemer
Procurement lead time (1)
5/25/11
6/29/11
25
0
AWARD
6/29/11
6/30/11
1
0
Fabricate for delivery
6/30/11
9/22/11
60
0
Item 3: New Backing Plates
8/6/12
9/28/12
39
0
20
Prep Requisition and procurement package
8/6/12
8/8/12
2
0
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski
SUBMIT REQ TO PROCUREMENT
8/8/12
8/9/12
1
0
Kelsey Tresemer
Kelsey Tresemer
Procurement lead time (1)
8/9/12
8/30/12
15
0
AWARD
8/30/12
8/31/12
1
0
Delivery
8/31/12
9/28/12
20
0
Pre-Assemble Armor
9/28/12
11/20/12
37
0
Fabricate Backing Plates
9/28/12
10/19/12
15
0
Craig Priniski
Craig Priniski, Fabrication Tech #1, Fabrication Tech #2
Assemble Armmor Quad #1
10/19/12
10/30/12
7
0
Fabrication Tech #1
Fabrication Tech #1, Fabrication Tech #2
Assemble Armmor Quad #2
10/30/12
11/6/12
5
0
Fabrication Tech #1
Fabrication Tech #1, Fabrication Tech #2
Assemble Armmor Quad #3
11/6/12
11/13/12
5
0
Fabrication Tech #1
Fabrication Tech #1, Fabrication Tech #2
Assemble Armmor Quad #4
11/13/12
11/20/12
5
0
Fabrication Tech #1
Fabrication Tech #1, Fabrication Tech #2
Assembly Procedure Finalized
2/16/12
3/8/12
15
0
Kelsey Tresemer
Kelsey Tresemer, Craig Priniski
Outage Begins
8/29/12
8/30/12
1
0
Installation
8/30/12
12/22/12
82
0
In Vessel Work Remove Armor
8/30/12
9/27/12
20
0
Machine Tech #1
Machine Tech #1, Fabrication Tech #1
Armor Support Installation
9/27/12
10/11/12
10
0
8
Kelsey Tresemer
Kelsey Tresemer, Machine Tech #1, Fabrication Tech #1
Armor Quadrent Instalations
11/20/12
12/11/12
15
0
Fabrication Tech #1
Craig Priniski, Machine Tech #1, Fabrication Tech #1
Sevice Connections
12/11/12
12/15/12
4
0
Machine Tech #1
Machine Tech #1, Fabrication Tech #1
Bay-H Port Cover Install
12/17/12
12/20/12
3
0
Craig Priniski
Craig Priniski, Machine Tech #1, Fabrication Tech #1
Testing
12/20/12
12/22/12
2
0
Craig Priniski
Craig Priniski, Machine Tech #1
Outage Ends
10/1/14
10/2/14
1
0

Ganttproject (2.0.10)ganttproject.biz
9/8/10 - 12:00:00 AM