From: Timothy N. Stevenson
Sent: Thursday, September 30, 2010 4:13 PM
To: Alfred von Halle
Cc: Mike Williams; Erik D. Perry; Mark B. Cropper; John W. Edwards;
Thomas E. Egebo; Masayuki Ono; Ronald L. Strykowsky; Mike Viola; Martin
Denault; Craig D. Priniski; S. Ramakrishnan; Guy Rossi; Neway Atnafu; Charles
A. Gentile; Tiana Dodson; Kristopher R. Gilton; John Winkelman; John Mitchell;
Brian Clark; Jerome Siegel; Lawrence E. Dudek; Kelsey Tresemer; Bob Simmons;
Orlando Guzman; Victor Garzotto; Carl M. Tilson; George Ascione; Keith R. Rule;
Maria L. Pueyo; Patricia M. Bruno; Robert A. Hitchner; Richard (Pete) Szaro
Subject: NBI Upgrade Weekly Status 10/1/10
Al,
NBI
Upgrade: Preparation for the upcoming EIR Cost and Schedule validation
review next week continues. Adjustments to the resource loaded schedule to
accurately reflect workflow leading up to FDR and then beyond are in progress.
Design work continues on VV modifications, Duct, Armor, and TVPS. Duct assembly
drawings are largely complete. Armor support models are nearing completion
allowing detailed assembly and part drawings to be generated. Project
management attended the Integrated Project Team meeting with DOE this week.
NBI
Decon: Removal of external platforms, walkways, and peripheral manifolds has
been completed. Low level decon on these items continues out on the 102'
platform in the Test Cell so these items can be moved out and stored for reuse
on BL2 in the NTC. After dispositioning these items, the Decon job will
be done. Some area maintenance has been performed this week to maintain the
Test Cell. Preparations have begun to start BL refurbishment on the BL
components.
Regards,
Tim
Timothy N. Stevenson, NBI
Project Manager
Head of Experimental Heating Systems
& Neutral Beam Operations
LSB 316 C Site
Princeton Plasma Physics Laboratory
Princeton University
P.O. Box 451
Princeton, NJ 08543
Office (609) 243-2657
FAX (609) 243-3248
email: tstevenson@pppl.gov
Skypager # : 2047351
You can visit the home page of the
DOE Princeton Plasma Physics Laboratory