NBI Decon:  Decon continued this week on the magnet, magnet shield, 
and 90 inch flange and neutralizers. Surveys indicate steady progress. A line 
break to access the OMA boxes was performed with no difficulty. Decon started on 
the outboard portions of the Lid LN cryo panels. Preparations continue for decon 
on the inboard portions. Additional equipment for this effort was ordered and 
has arrived. Some shield pieces have cleaned up well enough to remove them from 
the high contamination area. Packaging of material to be discarded has also 
begun. A rad laundry shipment has been scheduled also.
Regards,
Tim
Timothy N. Stevenson 
Head 
of Experimental Heating Systems & Neutral Beam Operations