From: Timothy N. Stevenson
Sent: Friday, May 06, 2011 9:23 AM
To: Mike Williams
Cc: Alfred von Halle; Erik D. Perry; Mark B. Cropper; John W. Edwards;
Thomas E. Egebo; Masayuki Ono; Yuhu Zhai; Ronald L. Strykowsky; Mike Viola;
Martin Denault; Kelsey Tresemer; William R. Blanchard; S. Ramakrishnan; Guy
Rossi; Neway Atnafu; Charles A. Gentile; Tiana Dodson; Kristopher R. Gilton;
John Winkelman; Brian Clark; Guy Grow; Lawrence E. Dudek; Bob Simmons; Orlando
Guzman; Victor Garzotto; Carl M. Tilson; George Ascione; Keith R. Rule; Maria
L. Pueyo; Patricia M. Bruno; Robert A. Hitchner; Richard (Pete) Szaro; Richard
J. Van Kirk
Subject: NBI Upgrade Weekly Status 5/6/11
Mike
NBI
Upgrade: Job status meetings were held this week with all active jobs
reporting progress toward FDR. Progress has been made on the VV prototype setup
in the Weld shop. Effort on drawings continues to prepare for the FDR. A
roughing valve location has been chosen and added to the TVPS design which
closes Peer Review chit #2. This location matches roughing line locations for
the new BL also. In house stock of CFC tile material has been identified for
use on the NBI Armor hot spot locations. This CFC material provides additional
strength in key areas and will be incorporated into the Armor design.
NBI
Refurbishment: Effort is underway to package a rad waste shipment
including the old ion dump plate. This effort will clear space needed for
further refurbishment activities. Machining of the new full energy ion dump
plate continues in the shop.
Regards,
Tim
Timothy N. Stevenson, NBI
Project Manager
Head of
Office of Project Management
Head of Experimental Heating Systems
& Neutral Beam Operations
LSB 316 C Site
Princeton Plasma Physics Laboratory
Princeton University
P.O. Box 451
Princeton, NJ 08543
Office (609) 243-2657
FAX (609) 243-3248
email: tstevenson@pppl.gov
Skypager # : 2047351
You can visit the home page of the
DOE Princeton Plasma Physics Laboratory