From: Timothy N. Stevenson
Sent: Thursday, March 04, 2010 6:06 PM
To: Alfred von Halle
Cc: Mike Williams; Erik D. Perry; Mark B. Cropper; John W. Edwards; Thomas E. Egebo; Masayuki Ono; Ronald L. Strykowsky; Michael Viola; Martin Denault; Craig D. Priniski; Subrahmanya Ramakrishnan; Guy Rossi; Neway Atnafu; Charles A. Gentile; Kristopher R. Gilton; John Winkelman; John Mitchell; Brian Clark; Jerome Siegel; Lawrence E. Dudek; Kelsey Tresemer; Bob Simmons; Orlando Guzman; Victor Garzotto; Carl M. Tilson; George Ascione; Keith R. Rule; Maria L. Pueyo; Patricia M. Bruno; Robert A. Hitchner; Richard (Pete) Szaro
Subject: NBI Upgrade Weekly Status 3/05/10
Al,

NBI Upgrade:  A successful NBIU Peer Review was held this week for all NBI Upgrade jobs to cover technical progress, analysis, and changes since the October CDR. Additionally, Decon status and plans, diagnostics accommodations, and recommendation responses  were presented and discussed. The review generated 6 chits which were minor in nature. The work presented will directly contribute to the WAF revision and review process scheduled for April and the PDR scheduled for June 2010. Project management attended the CS weekly meeting were much progress on analysis was presented.

NBI Decon:  Test Cell purge air quantities have been affected by the need to purge the NSTX Test Cell more aggressively due to bakeout. Additional mopping and wipe downs of equipment are  being performed to maintain areas in the Test Cell. Decon continued this week on lid and box. HP and ERWM support continues to be outstanding and keeps pace with events. So far, a total of 6 barrels have been solidified for disposal. Decon continued this week on lid and box. The sprayer is now being used at the 90 inch flange opening instead of from lifts beside the box. The box sprayer uses 25 gallons per decon pass. Most of the effluent water can be drained but  a slight amount of residual remains in the beamline and will have to be addressed prior to box entry and wipe downs of the interior. Plans to decon the ion dump are finalized and will begin with hands on wipe downs of the exterior and louvers. New breathable air system air lines were ordered to be used on the ion dump decon; hands on wipedowns of the ion dump will start when the air lines arrive. Evaluation of survey results are in progress in preparation for the Decon Peer Review planned for April 2010.

Regards,

Tim



Timothy N. Stevenson, NBI Project Manager

Head of Experimental Heating Systems & Neutral Beam Operations

LSB 316  C Site
Princeton Plasma Physics Laboratory
Princeton University
P.O. Box 451
Princeton, NJ 08543

Office (609) 243-2657
FAX (609) 243-3248
email: tstevenson@pppl.gov

Skypager # : 2047351


You can visit the home page of the DOE Princeton Plasma Physics Laboratory
at http://www.pppl.gov