NBI Decon: Decon wipedowns continued on the interior of the beam box.
Decon spray continued on the calorimeter. Decon continued on the ion dump
louvers in the fumehoods. Test Cell area maintenance has been performed on a
routine basis.
Timothy N. Stevenson, NBI Project Manager
Head
of Experimental Heating Systems & Neutral Beam Operations
LSB
316 C Site
Princeton Plasma Physics Laboratory
Princeton University
P.O.
Box 451
Princeton, NJ 08543
Office (609)
243-2657
FAX (609) 243-3248
Skypager # : 2047351
You can visit the home page of the DOE Princeton Plasma Physics
Laboratory