From: Timothy N. Stevenson
Sent: Friday, June 11, 2010 2:50 PM
To: Alfred von Halle
Cc: Mike Williams; Erik D. Perry; Mark B. Cropper; John W. Edwards;
Thomas E. Egebo; Masayuki Ono; Ronald L. Strykowsky; Michael Viola; Martin
Denault; Craig D. Priniski; S. Ramakrishnan; Guy Rossi; Neway Atnafu; Charles
A. Gentile; Kristopher R. Gilton; John Winkelman; John Mitchell; Brian Clark;
Jerome Siegel; Lawrence E. Dudek; Kelsey Tresemer; Bob Simmons; Orlando Guzman;
Victor Garzotto; Carl M. Tilson; George Ascione; Keith R. Rule; Maria L. Pueyo;
Patricia M. Bruno; Robert A. Hitchner; Richard (Pete) Szaro
Subject: NBI Upgrade Weekly Status 6/11/10
Al,
NBI
Upgrade: PDR dry run presentations took place on all NB jobs. Minor actions
items are being resolved and included. WAF scrutiny continues to refine
estimates.
NBI
Decon: Decon wipedowns continued on the interior of the beam box. Decon
spray continued on the calorimeter. Decon continued on the ion dump louvers in
the fumehoods. Levels continue to drop. Test Cell area maintenance has been
performed on a routine basis. The Test Cell area was configured to allow an
NSTX source to traverse the Test Cell to the Mockup Building for maintenance
which is the first such occasion since the Decon job was started. This
successful maneuver is a prelude to the process that will be involved for the
Upgrade Relocation job where equipment will be staged and moved into the NSTX
Test Cell.
Regards,
Tim
Timothy N. Stevenson, NBI Project
Manager
Head of Experimental Heating Systems
& Neutral Beam Operations
LSB 316 C Site
Princeton Plasma Physics Laboratory
Princeton University
P.O. Box 451
Princeton, NJ 08543
Office (609) 243-2657
FAX (609) 243-3248
email: tstevenson@pppl.gov
Skypager # : 2047351
You can visit the home page of the
DOE Princeton Plasma Physics Laboratory