From:                              Timothy N. Stevenson

Sent:                               Friday, July 30, 2010 10:22 AM

To:                                   Alfred von Halle

Cc:                                   Mike Williams; Erik D. Perry; Mark B. Cropper; John W. Edwards; Thomas E. Egebo; Masayuki Ono; Ronald L. Strykowsky; Michael Viola; Martin Denault; Craig D. Priniski; S. Ramakrishnan; Guy Rossi; Neway Atnafu; Charles A. Gentile; Kristopher R. Gilton; John Winkelman; John Mitchell; Brian Clark; Jerome Siegel; Lawrence E. Dudek; Kelsey Tresemer; Bob Simmons; Orlando Guzman; Victor Garzotto; Carl M. Tilson; George Ascione; Keith R. Rule; Maria L. Pueyo; Patricia M. Bruno; Robert A. Hitchner; Richard (Pete) Szaro

Subject:                          NBI Upgrade Weekly Status 7/30/10

 

Al,

 

NBI Upgrade: Project Management participated in preparations for the upcoming Office of Science review of the NSTX upgrade project. key talks were developed, presented, and critiqued. The NBI Duct model has been updated with flange and port details per a recent meeting.

 

NBI Decon:  Decon included cryo pipes, source platform, and low level items. Test Cell area maintenance has been performed on a routine basis. Planning and preparation for taking core samples of the copper on the ion dump has begun.

 

Regards,

 

Tim

 

 

 

Timothy N. Stevenson, NBI Project Manager                                                

                                               

Head of Experimental Heating Systems & Neutral Beam Operations

 

LSB 316  C Site                                                  

Princeton Plasma Physics Laboratory

Princeton University           

P.O. Box 451

Princeton, NJ 08543

 

Office      (609) 243-2657                                   

FAX                         (609) 243-3248

email:     tstevenson@pppl.gov                                        

 

Skypager # : 2047351

 

 

You can visit the home page of the DOE Princeton Plasma Physics Laboratory

at http://www.pppl.gov