NBI Upgrade: WAF cost and schedule preparation for all jobs continued this
past week. The NBIU BL2 Cost and Schedule Review has been scheduled for next
week. NBIU upgrade photos and status reports have been posted to the
upgrade website.
NBI Decon: The Lid Stand stairs and railings have been attached. The
procedure for removal of the magnet has been completed. Removal of the magnet is
schedule for next week. Decon continued on the calorimeter with steady progress
noted this week. Floor area preparation for locating the magnet stand and 90
inch flange stand is underway.