From: Timothy N. Stevenson
Sent: Thursday, July 23, 2009 6:50 PM
To: Alfred von Halle
Cc: Mike Williams; Erik D. Perry; Mark B. Cropper; John W. Edwards; Thomas E. Egebo; Masayuki Ono; Ronald L. Strykowsky; Michael E. Viola; Martin Denault; Craig D. Priniski; Subrahmanya Ramakrishnan; Guy Rossi; Charles A. Gentile; Kristopher R. Gilton; John Winkelman; John Mitchell; Brian Clark; Jerome Siegel; Lawrence E. Dudek; Kelsey Tresemer; Bob Simmons; Orlando Guzman; Victor Garzotto; Carl M. Tilson; George Ascione; Keith R. Rule; Maria L. Pueyo; Patricia M. Bruno; Robert A. Hitchner; Richard (Pete) Szaro
Subject: NBI Upgrade Weekly Status 7/24/09
Al,

NBI Upgrade: WAF cost and schedule preparation for all jobs continued this past week. The NBIU BL2 Cost and Schedule Review has been scheduled for next week.  NBIU upgrade photos and status reports have been posted to the upgrade website.

NBI Decon:  The Lid Stand stairs and railings have been attached. The procedure for removal of the magnet has been completed. Removal of the magnet is schedule for next week. Decon continued on the calorimeter with steady progress noted this week. Floor area preparation for locating the magnet stand and 90 inch flange stand is underway.


Regards,

Tim



Timothy N. Stevenson

Head of Experimental Heating Systems & Neutral Beam Operations

LSB 316  C Site
Princeton Plasma Physics Laboratory
Princeton University
P.O. Box 451
Princeton, NJ 08543

Office (609) 243-2657
FAX (609) 243-3248
email: tstevenson@pppl.gov

Skypager # : 2047351


You can visit the home page of the DOE Princeton Plasma Physics Laboratory
at http://www.pppl.gov