From: Timothy N. Stevenson
Sent: Thursday, July 16, 2009 11:48 AM
To: Alfred von Halle
Cc: Mike Williams; Erik D. Perry; Mark B. Cropper; John W. Edwards; Thomas E. Egebo; Masayuki Ono; Ronald L. Strykowsky; Michael E. Viola; Martin Denault; Craig D. Priniski; Subrahmanya Ramakrishnan; Guy Rossi; Charles A. Gentile; Kristopher R. Gilton; John Winkelman; John Mitchell; Brian Clark; Jerome Siegel; Danny Mangra; Lawrence E. Dudek; Kelsey Tresemer; Bob Simmons; Orlando Guzman; Victor Garzotto; Carl M. Tilson; George Ascione; Keith R. Rule; Maria L. Pueyo; Patricia M. Bruno; Robert A. Hitchner; Richard (Pete) Szaro
Subject: NBI Upgrade Weekly Status 7/17/09
Al,

NBI Management: Cost and schedule preparation continues. The biweekly CD1 job status is complete. Photos for the upgrade website have been gathered for use. Discussions with ERWM and HP took place to insure compliance with processing rad waste from the decon effort.

NBI Decon:  The Lid Stand was moved from the RESA shop into the Test Cell and positioned on the Test Cell floor. Decon of the calorimeter continues. Surveys continue to show reduction of contamination levels across the board. Preparations to remove the BL4 TIV and exit spool piece are underway. Preparations to remove the magnet and 90 inch flange are also underway.

NBI Relocation: Evaluation of lift fixture concepts and details continues to optimize clearance height and ease of attachment.

NBI Power and Control:  Focus continues on cabling and connections within the NTC. The controls cost estimate development continues.

NBI Duct, VV Port:  The rearrangement of the TVPS portion of the duct has been simplified and remodeled to maintain aisleways.

NBI Armor: Research of material specifications for tile thermal analysis continues.

NBI BL Services: Cost data is being collected and tallied for the estimate later this month.

NTC Equipment Relocations:  The relocation scope has been refined with additional diagnostics data. The cost estimating process is underway and nearing completion.


Regards,

Tim



Timothy N. Stevenson

Head of Experimental Heating Systems & Neutral Beam Operations

LSB 316  C Site
Princeton Plasma Physics Laboratory
Princeton University
P.O. Box 451
Princeton, NJ 08543

Office (609) 243-2657
FAX (609) 243-3248