NBI Decon: The large capacity sprayer needed for the box decon has
arrived and is being fitted out for use. Box decon is schedule to start next
week. Initial surveys of the box indicate contamination levels ranging
from 2 to 25 million dpm/100 cm2 depending on line of sight to the torus
opening. A standup meeting with NBI, ERWM, and HP ironed out some details
regarding removal of water from the box to drums which will greatly simplify the
handling of contaminated water effluent. Decon continued on the lid, magnet, and
90 inch flange. Some OMA box disassembly has begun to remove shields and allow
greater access. All indications are that levels continue to decline. Planning
for decon and partial disassembly of the ion dump has started. A full survey of
the ion dump was performed to benchmark this unit.
Regards,
Tim
Timothy N. Stevenson
Head
of Experimental Heating Systems & Neutral Beam Operations
LSB
316 C Site
Princeton Plasma Physics Laboratory
Princeton University
P.O.
Box 451
Princeton, NJ 08543
Office (609)
243-2657
FAX (609) 243-3248
Skypager # : 2047351
You can visit the home page of the DOE Princeton Plasma Physics
Laboratory