NBI Decon: Decon on lid and box continued this week using sprayers.
Very significant reductions in contamination on the beamline walls have been
noted in recent surveys. The floor levels are declining but at a slower rate
because the floor is the collection point for the effluent water. Preliminary
work on the ion dump is scheduled to start perhaps as soon as next week. HP and
ERWM support continues to fully keep pace with the progress of the job. A rad
laundry shipment has been collected and is scheduled to get moved out of the
Test Cell sometime in the next week.