NBI Decon: Decon continued on the ion dump and the interior of the
beam box this week. Area maintenance was also performed. Based on items reported
at the Decon Peer Review, decon on specific areas will be continued. A test to
determine if any regrowth can be noted is being performed over the next two
weeks.
Regards,
Tim
Timothy N. Stevenson, NBI Project Manager
Head