From: Lawrence E. Dudek Sent: Monday, September 26, 2011 3:06 PM To: NSTX Center Stack Upgrade Team Cc: Tiana Dodson; Bob Simmons Subject: Notes from Weekly Meeting 9/21 Notes from 9/21/2011 Meeting: Four week look ahead (Strykowsky) OH Conductor procurement released, 9/21. TF Bundle Molds released, 9/23 & Bellows formed Bellows released, 9/23 CS High Bay cluttered with new objects which have been moved in, cryo system from NCSX mod. coil test, etc. HVAC upgrade needs to be completed for winding area to become operational. OPEN Action: Labik to pre-order materials for the construction of the MPTS vacuum interface. Review of chits needed for Lehman review (Strykowsky) Only two chits remain open: Chit 201106-06 & 201106-1 OPEN Action: Titus to provide response to B. Jedic to close out these chits. VV Dome Rib Update (Smith) (see vgs) Mark reviewed the latest iteration of the rib reinforcements beneath the umbrella legs. While it improved the stresses in the ribs it did not go far enough. While try to add more weld to the tabs sides to see if that might reduce the stresses further. OTF Clevis Pin Analysis (Rogoff) (see vgs) Clevis connection looks okay except for the pin. Stresses in the pin are approx. 180 ksi. Pete suggested modifying the outer leg clevis connection to include 2 pins. Action:Mark and Pete to work out a solution. VV Buckling Analysis (Han) (see vgs) Han completed the buckling analysis, the safety factor against buckling for the VV is greater than 9.0. Action: Neway to work with Han and Pete to have the upgraded NB cap incorporated into the buckling analysis. GRD Rev 4 (Menard) (see vgs) Jon reviewed the changes made to the shot spectrum in GRD Rev 4 and explained how it compared to the existing operational limits. http://nstx-upgrade.pppl.gov/Project_Meetings/CenterStackUpgrade/index_Meetings.htm