From: Ronald L. Strykowsky
Sent: Thursday, July 07, 2011 2:33 PM
To: Ali Zolfaghari; Andrei Khodak; Arthur W. Brooks; Barry Jedic; Bob
Simmons; Charles L. Neumeyer; Erik D. Perry; George W. Labik; Han Zhang; Irving
J. Zatz; James H. Chrzanowski; Jonathan E. Menard; Judith A. Malsbury; Kelsey
Tresemer; Larry Bryant; Lawrence E. Dudek; Mark B. Cropper; Mark Smith; Martin
Denault; Masayuki Ono; Michael Mardenfeld; Mike Viola; Mike Williams; Neway
Atnafu; Orlando Guzman; Paul Sichta; Peter Rogoff; Peter Titus; Phil
Heitzenroeder; Robert D. Woolley; Robert Kaita; Ronald E. Hatcher; Ronald L.
Strykowsky; S. Ramakrishnan; Steve Raftopoulos; Thomas E. Egebo; Thomas G. Meighan;
Tiana Dodson; Timothy N. Stevenson; Tom Kozub; William R. Blanchard; Yuhu Zhai;
Lawrence E. Dudek; Steve Raftopoulos
Subject: FW: Reminder: NSTX CSU Project Meeting Tomorrow at 2:30
Attachments: 20110707 NSTX UPGRADE Calculations rls.xls; FDR chits.xls
Notes
from July 6, 2011 NSTX Upgrade team meeting.
1. Discussed
expectations and responsibilities of the calculation preparer. Bob
suggested modifications to the signoff page. Eng-003 will be revised to clarify
the role of the preparer, reviewer and cog engineer.
a.
Discussions also revealed the need for a calculation interface
matrix that shows the interdependencies between calculations. Bob Simmons will
draft a matrix for review. Additionally, the analysis models used as a basis
for calculations are not under configuration control. Needs further follow-up.
2. Plan for signing-off all remaining
calcs (by August??). Reviewed status of all calculations Status to date
(Attached). Discussed the need for a plan for having all calcs signed before
September. Pete and Phil to develop.
i.
Total
calcs=49
ii.
Number
prepared = 45
iii.
Reviewed
and sent to cog = 27
iv.
Signed
–off = 15
3. Resolution to the 16 chits generated
from the FDR. Updated Chits log (attached). Responses need from Titus,
Chrzanowski, Neumeyer
NSTX CS
Upgrade
scheduled
July 6, 2011 from 2:30 PM to 4:00 PM
Location:
New Engineering Conference Rm.
Agenda
Items:
1.
Expectations and responsibilities of the calculation preparer (Bob
Simmons)
2. Plan for
signing-off all remaining calcs (by August??). (Heitzenroeder/Titus)
3.
Resolution to the 16 chits generated from the FDR. Establish a response
and an action plan (who, what, and when)
4.
Definition of when the analysis work is complete which will mark the transition
into title III engineering support of procurement, construction, fabrication
etc