From:                              Ronald L. Strykowsky

Sent:                               Thursday, July 07, 2011 2:33 PM

To:                                   Ali Zolfaghari; Andrei Khodak; Arthur W. Brooks; Barry Jedic; Bob Simmons; Charles L. Neumeyer; Erik D. Perry; George W. Labik; Han Zhang; Irving J. Zatz; James H. Chrzanowski; Jonathan E. Menard; Judith A. Malsbury; Kelsey Tresemer; Larry Bryant; Lawrence E. Dudek; Mark B. Cropper; Mark Smith; Martin Denault; Masayuki Ono; Michael Mardenfeld; Mike Viola; Mike Williams; Neway Atnafu; Orlando Guzman; Paul Sichta; Peter Rogoff; Peter Titus; Phil Heitzenroeder; Robert D. Woolley; Robert Kaita; Ronald E. Hatcher; Ronald L. Strykowsky; S. Ramakrishnan; Steve Raftopoulos; Thomas E. Egebo; Thomas G. Meighan; Tiana Dodson; Timothy N. Stevenson; Tom Kozub; William R. Blanchard; Yuhu Zhai; Lawrence E. Dudek; Steve Raftopoulos

Subject:                          FW: Reminder: NSTX CSU Project Meeting Tomorrow at 2:30

Attachments:                 20110707 NSTX UPGRADE Calculations rls.xls; FDR chits.xls

 

Notes from July 6, 2011 NSTX Upgrade team meeting.

 

1.      Discussed expectations and responsibilities of the calculation preparer. Bob suggested modifications to the signoff page. Eng-003 will be revised to clarify the role of the preparer, reviewer and cog engineer.

a.      Discussions also revealed the need for a calculation interface matrix that shows the interdependencies between calculations. Bob Simmons will draft a matrix for review. Additionally, the analysis models used as a basis for calculations are not under configuration control. Needs further follow-up.

2.      Plan for signing-off all remaining calcs (by August??). Reviewed status of all calculations Status to date (Attached). Discussed the need for a plan for having all calcs signed before September. Pete and Phil to develop.

                                                              i.      Total calcs=49

                                                            ii.      Number prepared = 45

                                                          iii.      Reviewed and sent to cog = 27

                                                           iv.      Signed –off = 15

3.      Resolution to the 16 chits generated from the FDR.  Updated Chits log (attached). Responses need from Titus, Chrzanowski, Neumeyer

 

 

 

 

 

NSTX CS Upgrade

scheduled July 6, 2011 from 2:30 PM to 4:00 PM

Location: New Engineering Conference Rm.

Agenda Items:

1. Expectations  and responsibilities of the calculation preparer (Bob Simmons)

2. Plan for signing-off all remaining calcs (by August??). (Heitzenroeder/Titus)

3. Resolution to the 16 chits generated from the FDR.  Establish a response and an action plan (who, what, and when)

4. Definition of when the analysis work is complete which will mark the transition into title III engineering support of procurement, construction, fabrication etc