ECP-001 (Combine CA 770 and 7710
into one CA (7710) Direct Allocations)
-
ECP-002 (Move the baseline
start date for task 6100-0041 to 12 April 2012)
-
ECP-003 (Reduce man-hours on
task 6100-001. Add this budget as M&S on task 6100-0049D)
-
ECP-004 (1- CA
1304 change to TF procurement (cost/schedule) 2- CA 8200
re-structured and split into two CA's (8200/8210) 3- Remove four
tasks from NB Source CA 2420 4- Task acceleration)
-
ECP-005 (Update the Work
Breakdown Structure/Dictionary in the Project Execution Plan to
ensure that a single Control Account does not occur at more than
one WBS element)
-
ECP-006 (Various changes to
Control Accounts 7100 (move labor), 8200/8250 - delete WPs and
convert to PPs)
-
ECP-007 (Convert task
531-005 held in Planning Package to discrete tasks)
-
ECP-008 (Move budget/task (8200-0017A) for purchase of two welding machines from oversight job (8210) to field work job (8200). Change EVT
to % Complete)
-
ECP-009 (Control Account
3300: Convert WP 3300-125 EVT from Planning Package to %
complete)
-
ECP-010 (Convert EVT for
activity 531-013 to % complete)
-
ECP-011 (Control
Account 1002. Add scope (cost/schedule) as shown on attached WAF
to support reinforcement of passive plates. Change CA 1002 CAM
to Neway Atnafu)
-
ECP-012 (Delete
several unnecessary activities from CA 1304 Inner TF Bundle. Add
several activities (cost/schedule) to CA 1305 to accommodate
sandblast and prime of OH conductor. Reduce budget on task
2480-0057)
-
ECP-013 (Move task 8200-0017
from Control Account 8210 to Control Account 8200)
-
ECP-014 (Change
the EVT for task 2485-0044A to C - % complete)
-
ECP-015 (Add
activities (cost/schedule) to accomplish Aquapour test
recommended at FDR)
-
ECP-016
(Engineering and Analysis work to support adding compliance to
the HHFW antennas. New CAM = Bob Ellis) (OPS Scope)
-
ECP-017(Neway Atnafu will replace
Martin Denault as the Control Account Manager for Control
Account 2425 BL Relocation)
-
ECP-018 (Resource change for
several activities in control account 2450, and a change to the
start date of several LOE tasks)
-
ECP-019 (Move tasks for drilling additional holes in outer TF flags (tasks 1301-0300 and 1301-0310) from Control Account 1301 to Control Account 8200)
-
ECP-020 (Change the start and finish dates for the three LOE
tasks in CA2425)
-
ECP-021 Replanning of work scope in Control Account 2425
to better fit project timing. Should equate to a slight budget
reduction.
-
ECP-022 Re-planning of Control Account 5200 for Digital Coil
Protection
-
ECP-023 (Transfer
responsibility of Control Account Manager (CAM) from Martin
Denault to Mark Cropper for Control Account 2440 2nd NBI
Beamline)
-
ECP-024 (Replace task 1307-2030 Fabricate CS Casing with five
(5) new tasks consistent with contract award)
-
ECP-025 In
Control Account 2475 add steps to the schedule for EPICS timing
and Control Interface. In Control Account 8200: Delete task
8200-0102C
-
ECP-026 Change M&S budget on
tasks 1001-0066 and 1001-0066F in Control Account 1001. Also
this ECP increases FY12 resources for CA 7100, and deletes
redundant tasks from CA 8250.
-
ECP-027
Update (replanning) of Control Accounts 1302, 1304, 1305 and
1307 including additional task deletions and updated resources.
Delete PP 8200-PP01A
-
ECP-028 Control Account 7300 - Delete task
7300-13 Support OPA Review
-
ECP-029 Re-define
Level II Milestone addressing TF conductors in both PEP and
Project Schedule
-
ECP-030 In
Control Account 7300 (NB Management) delete activity 7300-22
-
ECP-031 CA: 1002 Add drafting
support CA: 2440 Delete tasks for exit spool piece CA: 2490 Add
drafting support and tasks for locating TMP rack on 119'
platform
-
ECP-032
Not used
-
ECP-033 In
Control Account 1000 increase the Title III Analysis Support
task (LOE) to 900 man hours/FY. Reduce FY12 and FY13 HP
Allocation task in Control Account 7710.
-
ECP-034 Change the EVT for
several tasks in CA 1304 from 0-100 to % complete.
-
ECP-035 Change
baseline dates of LOE task 1304-1510 in Control Account 1305
-
ECP-036 Add
staightening of conductors task to Major Tool contract
(1304-1000, $66,260.00)
-
ECP-037 CHI Gap
Tiles for Control Account 1001
-
ECP-038 Not Used
-
ECP-039 Additional budget
to jobs in CA's 1300, 1301 and 1305. Resources are needed for
these tasks that were not previously budgeted
-
ECP-040 Physics
personnel identified new scope for Diagnostics. This ECP
represents the portion of that which Central I&C can service
(OPS Scope)
-
ECP-041 PF1 feed
changes (OPS Scope)
-
ECP-042 Reschedule and
re-budget task 8200-0012D "Reinstallation Oversight"
-
ECP-043 Additional tasks
for Control Accounts 8200 and 2490. Delete 3 tasks from CA 2490
-
ECP-044 HVAC duct
above door between TFTR and NSTX TC needs higher mounting - Not
yet submitted
-
ECP-045 Re-estimating of
remaining Center Stack Work
-
ECP-046 Delete tasks
1001-0078 and 1001-0082 in Control Account 1001. These two tasks
are redundant.
-
ECP-047 Change Control
Account Manager (CAM) for several jobs
-
ECP-048 Updated estimated
costs for Control Account 1200 are more than original budget for
several tasks
-
ECP-049
Additional scope (cost/schedule) for Control Account 5501
analysis tasks
-
ECP-050 Add additional
budget to oversight task 6100-0000
-
ECP-051 Add activity 1305-0003 to
re-design and manufacture flanges for the TF Quadrant Mold that
will allow for complete closure and sealing of the mold
-
ECP-052 Convert Planning
Package 2480-0076 to discrete activities
-
ECP-053 Delete tasks
2440-0014 and 2440-0024 from Control Account 2440
-
ECP-054 Delete
tasks 24910470 and 29410480 from Control Account 2490
-
ECP-055 Add scope
for analysis/design/fabrication/installation of tFIDA
-
ECP-056 Delete unnecessary
task from CA 2440. Add activities in CA 2475 for LCC refurb and
software upgrades
-
ECP-057 Install 6
small ports on NSTX Vacuum Vessel
-
ECP-058 For
Control Acct 1001 the contract for the machining of Batch 1 of
the PFCs came in under budget by ~$90K. For Control Acct 2460
there is an increase in job scope
-
ECP-059 Move BL start date
for task 1001-0066F to 12/3/2012 while task is being replanned.
-
ECP-060 ECP
required to request funding for additional work that was not
included in the Planning Package (Control Account 2450). It
includes water pipe install in NTC, drawings, pressure testing.
-
ECP-061
Add tasks to cover additional work on TF quadrant mold and to
perform an in-line braze test (OH). Change BL dates on two other
tasks.
-
ECP-062
For Control Account 8200/8210 - add re-work of
parts received from other WBS elements. Delete two tasks from
Management Job 7300 and one task from Management Job 7200.
-
ECP-063 Change BL start and
finish dates on Water PLC portion of DCPS (5200) job.
-
ECP-064 Coil
Bus Run - Overhaul of Control Account (Replanning/Updated
budget)
-
ECP-065
Change Control Account Manager (CAM) on Control Account 5501
Coil Bus Runs to Neway Atnafu
-
ECP-066 Passive Plate
Reinforcement
-
ECP-067
Remove several activities from Control Account 2490 which are no
longer required since the SPRED diagnostic will not be
re-installed
-
ECP-068 Correct baseline
dates for various future Critical Path activities to make them
consistent with the baseline and milestones. Also, replan
activity 1306-5-5 for the PF coil procurement
-
ECP-069 Reduce total budget
on task 1001-0066F to $142,000 (a reduction of $146,064.80)
-
ECP-070 Move
baseline dates for task 1305-2620 "Fab and Deliver OH Mold"
-
ECP-071 Reduction of 10% in
remaining HP support activities and HP direct allocations due to
reduced need.
-
ECP-072
Control Account Manager restructuring of job post CAM change. No
increase in budget
-
ECP-073
NOT USED
-
ECP-074
S-FLIP port installation and reinforcement
-
ECP-075
NOT USED
-
ECP-076
Adjust the baseline dates of various future tasks in job 1001
Plasma Facing Components (small increase due to tasks pushed
into FY14)
-
ECP-077 In Control Account
8200 add additional scope for installation of umbrella arch
reinforcements which is not included in the existing estimate
-
ECP-078 Updated resources
for CA 1300/1305 to cover the VPI's through the full TF,
Engineering Support, Title III work. Also added task/budget for
commissioning of OH Winding Station
-
ECP-079 In
Control Account 1200. The bolted connection between the lower
lid and the pedestal require re-design and analysis
-
ECP-080 Delete Planning
Package 8250-PP01A "CS Analysis Update". This scope is not
needed in this Control Account
-
ECP-081 Delete current task
1306-5050A for the PF Coil Procurement and replace with new task
1306-5050B which shows the current contract price/schedule
-
ECP-082
Budgeted time required for Control Account 1300 task 1300-0012
Engineering Support needs to be increased 300 hrs. per month
through Sept. 2013
-
ECP-083 NOT
USED
-
ECP-084
The winning bid for the NBI Pipeline construction
contract was $668,210. This is more than the $500,000 originally
estimated by $168,210. Plus, due to safety concern for this
complex construction activity, 1 PPPL personnel is decided to
monitor and assist the contractor activities at all times, in
addition to the supervision by Technical Rep, QC and ES&H
-
ECP-085
Additional tasks required in Control Account 8250
required for the re-assembly of the Centerstack and Installation
into NSTX. These tasks are off-set by several tasks being
deleted.
-
ECP-086 The
schedule for Control Account 5200 was no longer effective. This
ECP stops the previous schedule (w/ exceptions) and adds the
activities as attached. -
-
ECP-087 Delete unnecessary
tasks from Control Account 2480. Add new steps for the
fabrication, testing and assembly of the transition duct.
-
ECP-088 Control Account
1200: Requires high strength hardware for all umbrella
upper/lower lid connection. Additional M&S required.
-
ECP-089 In job 1305 add two
additional tasks 1) Additonal OH conductor 2) Provide
dehumidifier for CS HiBay
-
ECP-090 Additional task in
Control Account 720-0 to cover estimated costs of attending SOFE
Conference.
-
ECP-091 Control Account
3300: Purchase additional Bakeout System Power Supplies/accessories
-
ECP-092
Control Account 5200 requires
additional scope to support: 1) Computer Division Support
Activities, 2) Additional Computer Division project oversight,
3) Evaluation of additional scope requirements, and 4)
Additional software design. (Not yet submitted)
-
ECP-093
Change the
Control Account Manager for Control Accounts 2425 and 2450 from
Neway Atnafu to Mark Cropper
-
ECP-094 Increased budget
need on several activities in Control Account 5501 as a result
of a bottom up estimate. Estimate completed after increase in
design maturity.
-
ECP-095 PCHERS passive
plate design/fabrication
-
ECP-096 Increase budget on
task 247000750 "Installation of 2nd NB Raceway" due to
subcontract being higher cost than budgeted.
-
ECP-097 Add additional
budget to Control Account 1300 to extend LOE Engineering Support
-
ECP-098 NOT USED
-
ECP-099 Additional budget
to support coil winding activities in Control Account 1305
-
ECP-100 Fabricate, install,
and test a two turn RWM encompassing Bays A and L
-
ECP-101 Additional scope
required in Control Account 8250 to prepare/install the OTF flex
joints. This work will require the fabrication of 72 unique
spacers to connect the OTF flex joints.
-
ECP-102 In control account
6100 add an additional $13,050 to activity 6100-0049D for an
upgraded LEMOPANEL to resource 41 (M&S)
-
ECP-103 Add additional task
in CA 1305 for three (3) additional five gallon kits of CTD 425
which are expected to be needed for the OH coil VPI
-
ECP-104 Control Account
1300 requires additional Engineering/Design support through May
2014
-
ECP-105 In Control Account
1305 add tasks previously identified to BL. These are tasks
identified by the CAM that occur after the OH VPI.
-
ECP-106 Control Account 1200
requires additional labor to complete documentation
-
ECP-107
In Control Account 6100 it appears as though an error was made
when entering information into Primavera from the WAF and the
second digit of the budgeted hours was clipped for activity
6100-0073A. A spreadsheet and screenshot from WAF is attached.
This ECP corrects the budgeted hours (increased cost).
-
ECP-108 NOT USED
-
ECP-109
DCPS (Control Account 5200) additional scope: Prepare/Install
DCPS computer, Halmar Signal Conditioner interface box, Temp.
conn. panel, RTC interface chasis, IT and Management Support.
-
ECP-110
A review of Control Account 3200 (Cooling Water) indicated a
budget need. The current unstarted activities will be deleted an
replaced by the activities shown on the attached WAF.
-
ECP-111
In Control Account 8200 delete activity 8200-0110
"Adjust PF Coils". Due to the nature of how work was performed
this activity is no longer required to be performed. Add an
additional task to Control Account 8200 to remove gaps around
the TFOL Al block interface using epoxy. Increase cost due to
man hours for this field work.- PENDING
-
ECP-112
Move the baseline start and finish dates
for several tasks. In 7100 for ORA Support, and in 2490 move the
installation tasks for the reinstall of the IR Camera(s),
LOWEUS, and Transmission Grating Spectrometer due unclear path
forward.
-
ECP-113
In Control Account 1304 delete
activity 1304-1154 "Fab/Deliver supports for OTF jumpers" and
replace with new activity capturing the updated cost/schedule
for the fabrication and delivery of these parts.
-
ECP-114
Revise PEP Level II milestone "Complete fab & test inner TF/OH
assembly from June 2014 to July 2014
-
ECP-115 In Control Account
1300 add additional EA//EM oversight resources through July 2014
-
ECP-116 In 1306 the S/C for
the PF coils has been changed to provide equitable adjustment
and incentive
-
ECP-117 In 1304 add
Purchase Order PEO13500 has been issued for another set of outer
TF connectors (lead extensions. Also several changes in 8250
(replaced activities).
-
ECP-118 Add new activity in
1300 to provide Engineering Support through Sept 30th to support
CS fab
-
ECP-119 in Control Account
6100 the activities have been expanded for the PSRTC scope
-
ECP-120 NOT
USED
-
ECP-121 In Control account
8200 deleted RF piping installation activity, added misc. M&S to
support field work, in 8250 added activity to "Install OTF flag
supports", added LOE oversight in 8210
-
ECP-122 In Control Account
7900 deleted activity 7900-110
-
ECP-123 In Control Account
7100 move BL start/finish dates for activity CS7000052 "ORA
Support"
-
ECP-124 In Control Account
1002 delete activities associated with preparing/installing
Passive Plates in the machine
-
ECP-125 NOT
USED
-
ECP-126 Deleted 2490 scope
not required for CD-4
-
ECP-127 In Control Account
7200 CSU Management add LOE task for oversight through January
2015
-
ECP-128 In Control Account
7300 NB2 Management add LOE task for oversight through December
2014
-
ECP-129 In Control Account
7100 delete activity CS7000052 "ORA Support"
-
ECP-130 Move several
activities from 1305 to 1302
-
ECP-131 In
Control Account 7100 add LOE hours to support Project Management
activities through February 2015
-
ECP-132
In Control Account 1302 delete activity 1302-1600 "Tear down
assembly area". This activity to be performed by NSTXU
Operations. Job 1302 may be closed as a result
-
ECP-133
Add the following activities in 8250: 1. Re-machining of TF lead
extensions per request of Engineering 2. Health Physics coverage
for 8250 tasks
-
ECP-134
The cancellation of the (WBS5) FCPC Fault Detector project has
cancelled (WBS6) planned CAMAC retirement, so this ECP will
supplement the remaining CAMAC memory.