From: Lawrence E. Dudek Sent: Tuesday, January 11, 2011 10:15 AM To: NSTX Center Stack Upgrade Team Subject: Notes from CSU Project Meeting 1/5/2011 Attachments: 20110105 NSTX UPGRADE Calculations-RTS_11112010.xls; ATT959930.htm Notes from 1/5 Meeting: Reviewed the Analysis spreadsheet (See Attached) Updated spreadsheet attached with overall progress curve. In order to keep the calculation progress on track for the FDR, project will need to complete 3-4 calculations per week. Update PF 4 & 5 supports and VV Clevis (Titus) (see VGs) Latest analysis of the VV clevis indicates that the preliminary design will work without welding to the vessel. Analysis on the PF 4 & 5 supports using various heating and cooling scenarios of the coils indicates a need for compliance in the radial direction to reduce stresses in the PF coils. One solution is to use a pinned link which would allow for the thermal growth of the coils. PAST ACTION ITEMS: COMPLETED -Neumeyer updated and reissued the GRD with new design point spreadsheet using the new influence matrix data provided by Hatcher. COMPLETED - M. Smith provided models of the latest support hardware to TItus for incorporation into the models. -Titus to provide (item 39) coupled DCPS moment influence coefficients to Hatcher (12/15) Viewgraphs will be posted by B. Simmons at: http://nstx-upgrade.pppl.gov/Project_Meetings/CenterStackUpgrade/index_Meetings.htm