National Spherical Torus Experiment (NSTX) Upgrades
Engineering Change Proposal Status
NSTX Upgrade Projects Configuration Control Procedure
ECP |
Title |
Class of ECP |
Date Submitted |
Date Approved |
Master Schedule | Summary Schedule | Cost Table by WBS | Cost Profile by FY | Table of Milestones |
ECP-001 |
Capture two direct allocation accounts in one account |
3 | 06/02/2011 | 06/03/2011 | N/A | N/A | N/A | N/A | N/A |
ECP-002 |
Move the BL Start date for task 6100-0041 to 12April2012 |
3 | 06/07/2011 | 06/08/2011 | N/A | N/A | N/A | N/A | N/A |
ECP-003 |
Reduce man‐hours on task 6100‐0041. Add this budget as M&S in task 6100‐0049D |
3
|
9/14/2011 | 9/19/2011 | N/A | N/A | N/A | N/A | N/A |