National Spherical Torus Experiment (NSTX) Upgrades

Engineering Change Proposal Status


 

NSTX Upgrade Projects Configuration Control Procedure

ECP

Title

Class of ECP

Date Submitted

Date Approved

Master Schedule Summary Schedule Cost Table by WBS Cost Profile by FY Table of Milestones
                   
ECP-001

Capture two direct allocation accounts in one account

3 06/02/2011 06/03/2011 N/A N/A N/A N/A N/A
ECP-002

Move the BL Start date for task 6100-0041 to 12April2012

3 06/07/2011 06/08/2011 N/A N/A N/A N/A N/A
ECP-003

Reduce man‐hours on task 6100‐0041. Add this budget as M&S in task 6100‐0049D

3

 

9/14/2011 9/19/2011 N/A N/A N/A N/A N/A

 


Revised: 12/6/2010 / R. Simmons